6223 N COLUMBUS AVE 91411

Certificate Information: 6223 N COLUMBUS AVE 91411

Application / Permit
23014-20000-00091
Plan Check / Job No.
B23VN00132
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' GARAGE AND (N) 36' X 27'-5" ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) and (e). WORK PER ENGINEERING.
Permit Issued
Issued on 8/1/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2023 APPLICANT
Assigned to Plan Check Engineer 1/6/2023 MADISON ODELL
Corrections Issued 1/7/2023 MADISON ODELL
Building Plans Picked Up 1/17/2023 APPLICANT
Applicant returned to address corrections 6/21/2023 MOHAMMAD ESMAILI
Plan Check Approved 8/1/2023 ISIS ARGUETA
Issued 8/1/2023 APPLICANT
CofO in Progress 5/2/2025 RYAN SALAZAR
Permit Finaled 5/6/2025 RUBEN SALAS
Permit Finaled 5/6/2025 RUBEN SALAS
CofO Issued 5/6/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/1/2023 MEGAN GODINEZ
ZI Cleared 3/15/2023 ASHLEY RODARTE
Low Impact Development Cleared 6/20/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 6/21/2023 LEE GUILBEAUX
Address approval Cleared 7/17/2023 DAGOVERTO GUERRERO
Address approval Cleared 7/17/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 7/18/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Lerner,, George; Lic. No.: C40288 4668 WILLIS AVE      SHERMAN OAKS, CA 91403

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/2/2023 Partial Approval RAUL OLAGI
Special/Order Compliance 10/2/2023 Corrections Issued RAUL OLAGI
Underground Mechanical 10/16/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 10/20/2023 Corrections Issued RYAN SALAZAR
METHANE-Barrier 10/20/2023 Approved RYAN SALAZAR
METHANE-Subgrade 10/20/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/28/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/22/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/18/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 4/18/2024 Approved RYAN SALAZAR
Green Building Rough 4/18/2024 Approved RYAN SALAZAR
HVAC-Rough 4/18/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/18/2024 Partial Approval RYAN SALAZAR
METHANE-Rough 4/18/2024 Approved RYAN SALAZAR
PLUMBING-Rough 4/18/2024 Approved RYAN SALAZAR
Insulation 5/9/2024 Corrections Issued LEONARD ROSS II
Insulation 7/2/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/2/2024 Approved RYAN SALAZAR
Drywall Nailing 8/28/2024 Approved MICHAEL CORTEZ
Final 12/4/2024 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 12/4/2024 Approved RYAN SALAZAR
Green Building Final 12/4/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/4/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 12/4/2024 Approved RYAN SALAZAR
Final 12/26/2024 No Access for Inspection RYAN SALAZAR
Final 4/7/2025 Not Ready for Inspection JOSE AVILA
Final 5/1/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 5/1/2025 Approved RYAN SALAZAR