6857 N MATILIJA AVE 91405

Certificate Information: 6857 N MATILIJA AVE 91405

Application / Permit
23014-20000-00071
Plan Check / Job No.
B23VN00076
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND INT REMODEL
Permit Issued
Issued on 4/20/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2023 APPLICANT
Assigned to Plan Check Engineer 1/6/2023 SERGIO MUNIZ
Corrections Issued 1/9/2023 SERGIO MUNIZ
Building Plans Picked Up 1/10/2023 APPLICANT
Plan Check Approved 2/6/2023 JESSE ARELLANO
Issued 4/20/2023 APPLICANT
CofO in Progress 12/18/2023 RYAN SALAZAR
Permit Finaled 4/15/2024 DANIEL ORRANTE
CofO Issued 4/15/2024 DANIEL ORRANTE
Permit Finaled 4/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 2/3/2023 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 2/6/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/6/2023 CARLOS AGUILERA
Sewer availability Cleared 2/6/2023 CARLOS AGUILERA

Contact Information

Contractor I D C S Corporation; Lic. No.: 995061-B 9854 NATIONAL BLVD #162      LOS ANGELES, CA 90034
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/26/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 5/30/2023 Approved RYAN SALAZAR
Insulation 6/5/2023 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 6/5/2023 Partial Approval RYAN SALAZAR
Wood Frame 6/5/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/11/2023 Not Ready for Inspection RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 7/11/2023 Approved RYAN SALAZAR
Green Building Rough 7/11/2023 Not Ready for Inspection RYAN SALAZAR
Piling/Pier/Caisson 7/11/2023 Not Ready for Inspection RYAN SALAZAR
Underground Mechanical 7/11/2023 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 8/1/2023 Approved RYAN SALAZAR
HVAC-Rough 8/1/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/1/2023 Partial Approval RYAN SALAZAR
PLUMBING-Rough 8/1/2023 Approved RYAN SALAZAR
Wood Frame 8/1/2023 Approved RYAN SALAZAR
Insulation 8/4/2023 Approved JUAN VALENZUELA
Drywall Nailing 8/14/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/14/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 10/16/2023 Not Ready for Inspection RYAN SALAZAR
HVAC-Final 10/16/2023 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Final 10/16/2023 Not Ready for Inspection RYAN SALAZAR
Service/Power Release 10/16/2023 Not Required RYAN SALAZAR
BUILDING-Rough-Frame 12/1/2023 Approved RYAN SALAZAR
Final 12/1/2023 Corrections Issued RYAN SALAZAR
Green Building Final 12/1/2023 Approved RYAN SALAZAR
Green Building Rough 12/1/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/1/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 12/1/2023 Approved RYAN SALAZAR
Final 12/15/2023 OK to Issue CofO RYAN SALAZAR
Service/Power Release 12/15/2023 Approved RYAN SALAZAR