3023 1/2 S GLENDON AVE 90034

Certificate Information: 3023 1/2 S GLENDON AVE 90034

Application / Permit
23014-20000-00054
Plan Check / Job No.
B23VN00055
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET GARAGE TO ACCESSORY DWELLING UNIT W/ 5' x 10'-6" ADDITION [PER LAMC 12.22 A.33 (c)-(d)]; ALL WORK PER ENGINEERING DESIGN
Permit Issued
Issued on 3/6/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2023 APPLICANT
Assigned to Plan Check Engineer 2/9/2023 SEAN SHAHMIRI
Corrections Issued 2/13/2023 SEAN SHAHMIRI
Quality Review Completed 2/16/2023 OMID HEDAYAT
Building Plans Picked Up 2/21/2023 APPLICANT
Applicant returned to address corrections 5/9/2023 SEAN SHAHMIRI
Plan Check Approved 5/23/2023 SEAN SHAHMIRI
Issued 3/6/2024 APPLICANT
CofO in Progress 8/5/2024 JESUS PINEDA
Permit Finaled 8/6/2024 DANIEL ORRANTE
CofO Issued 8/6/2024 DANIEL ORRANTE
Permit Finaled 8/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/28/2023 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 3/8/2023 JENSON LEE
Roof/Waste drainage to street Cleared 3/8/2023 JENSON LEE
Sewer availability Cleared 3/8/2023 JENSON LEE
Specific Plan Cleared 3/21/2023 JIMMY VIVAR
Hydrant and Access approval Cleared 5/5/2023 LAVEON RIDER
Construction within easement Cleared 5/15/2023 TINA MIRANDA

Contact Information

Contractor Ag Construction And Management Inc; Lic. No.: 1113828-B 20238 LANARK ST      WINNETKA, CA 91606
Engineer Chang,, Yeh; Lic. No.: S6868 168 S SIERRA MADRE BLVD 109      PASADENA, CA 91107

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2024 Partial Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 5/2/2024 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 5/2/2024 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Rough 5/2/2024 Corrections Issued ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 5/8/2024 Approved STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 5/8/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 5/8/2024 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Corrections Issued JESUS PINEDA
PLUMBING-Rough 6/18/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 6/25/2024 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 6/25/2024 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 6/25/2024 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 6/25/2024 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 6/27/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 6/27/2024 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 6/27/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 7/1/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 7/1/2024 Approved JESUS PINEDA
Green Building Rough 7/1/2024 Approved JESUS PINEDA
HVAC-Rough 7/1/2024 Approved JESUS PINEDA
MERV13>=Rough 7/1/2024 Approved JESUS PINEDA
Insulation 7/3/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 7/3/2024 Approved JESUS PINEDA
Drywall Nailing 7/8/2024 Approved ARAM AVEDISIAN
Final 7/25/2024 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 7/25/2024 Approved TEMISTOCLES CAAL
Green Building Final 7/25/2024 Approved TEMISTOCLES CAAL
MERV13>=Final 7/25/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 7/25/2024 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 7/25/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 7/26/2024 Corrections Issued STEPHANIE SWANSON
Final 7/26/2024 Corrections Issued STEPHANIE SWANSON
Grounding or Bonding 7/26/2024 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Final 7/26/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 7/26/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 7/30/2024 Approved JESUS PINEDA
Final 7/30/2024 Not Ready for Inspection JESUS PINEDA
Final 8/2/2024 OK to Issue CofO JESUS PINEDA
PLUMBING-Final 8/2/2024 Approved JESUS PINEDA