7019 N GEYSER AVE 91335
Certificate Information: 7019 N GEYSER AVE 91335
- Application / Permit
- 23014-20000-00050
- Plan Check / Job No.
- B22VN19252
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan Convert existing 493 Sq. Ft. detached garage into ADU with addition
- Permit Issued
- Issued on 2/20/2024
- Issuing Office
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2023 | JOSEPH RAFOLS |
| Corrections Issued | 1/14/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 3/7/2023 | JOSEPH RAFOLS |
| Issued | 2/20/2024 | APPLICANT |
| CofO in Progress | 11/6/2024 | ARUTYUN MADATYAN |
| Permit Finaled | 11/12/2024 | JOHN JANSON |
| CofO Issued | 11/12/2024 | JOHN JANSON |
| Permit Finaled | 11/12/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/25/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/26/2023 | CARLOS AGUILERA |
| ZI | Cleared | 2/7/2023 | YINGSHI HUANG |
Contact Information
| Contractor | Precision Home Remodeling Inc; Lic. No.: 1112627-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/26/2024 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 3/6/2024 | Not Ready for Inspection | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 3/6/2024 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 3/6/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 3/6/2024 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 3/6/2024 | Partial Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 3/15/2024 | Not Ready for Inspection | JEFFREY BULL |
| Pre-Inspection | 3/15/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 3/26/2024 | No Access for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2024 | Corrections Issued | HENRY KIM |
| Service/Power Release | 3/26/2024 | Partial Inspection | HENRY KIM |
| Underground Mechanical | 3/26/2024 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 3/29/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Gas Test | 3/29/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Light Gage Steel Frame | 3/29/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/29/2024 | Partial Approval | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/2/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 4/2/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 4/2/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 4/2/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 4/2/2024 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 4/2/2024 | Approved | JEFFREY BULL |
| Special/Order Compliance | 4/2/2024 | Corrections Issued | JEFFREY BULL |
| Insulation | 4/5/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 4/5/2024 | Approved | JEFFREY BULL |
| Shower Pan | 4/5/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 4/11/2024 | Approved | HENRY KIM |
| Sewer | 4/19/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 4/30/2024 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Final | 5/6/2024 | Approved | JEFFREY BULL |
| Service/Power Release | 5/6/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 10/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| Final | 10/9/2024 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 10/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Final | 10/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Final | 10/9/2024 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 10/9/2024 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 10/9/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 11/5/2024 | Approved | ARUTYUN MADATYAN |
| Final | 11/5/2024 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 11/5/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 11/5/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 11/5/2024 | Approved | ARUTYUN MADATYAN |