23225-23227 W LEONORA DR 91367
Certificate Information: 23225-23227 W LEONORA DR 91367
- Application / Permit
- 23014-20000-00049
- Plan Check / Job No.
- B22VN19251
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 16'10" x 37'2" ADDITION TO SFD, ADDITION TO EXTEND BREEZEWAY, AND INT REMODEL. WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/16/2023
- Issuing Office
- Current Status
- CofO Issued on 3/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2023 | ISIS ARGUETA |
| Corrections Issued | 1/14/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 8/25/2023 | ISIS ARGUETA |
| Plan Check Approved | 9/13/2023 | ISIS ARGUETA |
| Issued | 9/16/2023 | APPLICANT |
| CofO in Progress | 3/7/2025 | TROY SANDERS |
| Permit Finaled | 3/24/2025 | JOHN JANSON |
| CofO Issued | 3/24/2025 | JOHN JANSON |
| Permit Finaled | 3/24/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2023 | SHAELYN ROWEN |
| Sewer availability | Cleared | 2/17/2023 | SHAELYN ROWEN |
| Low Impact Development | Cleared | 8/14/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 8/24/2023 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 9/12/2023 | ISIS ARGUETA |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: NA24587 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/8/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Deputy Drilled-In Anchors | 6/5/2024 | Conditional Approval | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 6/7/2024 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Partial Approval | GEVORK IPCHYAN |
| Gas Test | 6/17/2024 | Approved | GEVORK IPCHYAN |
| Underground Mechanical | 6/17/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 6/20/2024 | Partial Approval | GEVORK IPCHYAN |
| MERV13>=Rough | 6/20/2024 | Approved | GEVORK IPCHYAN |
| Wood Frame | 6/20/2024 | Partial Approval | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 8/13/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 8/13/2024 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 8/13/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 8/13/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 8/13/2024 | Partial Approval | GEVORK IPCHYAN |
| PLUMBING-Rough | 8/13/2024 | Approved | GEVORK IPCHYAN |
| Insulation | 8/16/2024 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 8/21/2024 | Approved | GEVORK IPCHYAN |
| Shower Pan | 9/3/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 9/9/2024 | Approved | GEVORK IPCHYAN |
| Final | 2/19/2025 | Not Ready for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 2/19/2025 | Approved | TROY SANDERS |
| MERV13>=Final | 2/19/2025 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 2/19/2025 | Approved | TROY SANDERS |
| Smoke Detectors | 2/19/2025 | Approved | TROY SANDERS |
| Final | 3/5/2025 | OK to Issue CofO | TROY SANDERS |