17036 W OROZCO ST 91344

Certificate Information: 17036 W OROZCO ST 91344

Application / Permit
23014-20000-00045
Plan Check / Job No.
B22VN19248
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan** Remodel and 2snd floor addition of (E) Single Familly Dwelling.
Permit Issued
Issued on 3/16/2023
Issuing Office
Current Status
CofO Issued on 10/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2023 APPLICANT
Assigned to Plan Check Engineer 1/10/2023 EDWIN ESPIN
Corrections Issued 1/11/2023 EDWIN ESPIN
Plan Check Approved 3/15/2023 EDWIN ESPIN
Issued 3/16/2023 APPLICANT
CofO in Progress 10/5/2023 STEVEN BACK
Permit Finaled 10/11/2023 JOHN JANSON
CofO Issued 10/11/2023 JOHN JANSON
Permit Finaled 10/11/2023 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/27/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/31/2023 COLIN LOREDO
Grading Pre-Inspection Cleared 3/15/2023 EDWIN ESPIN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/10/2023 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 4/12/2023 Approved SEAN WIRCH
Special/Order Compliance 4/12/2023 Partial Inspection MORRIS JACKSON
Underground Mechanical 5/10/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Inspection STEVEN BACK
Deputy Wood Construction 5/26/2023 Conditional Approval STEVEN BACK
BUILDING-Rough-Frame 6/5/2023 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 6/5/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Approved STEVEN BACK
Green Building Rough 6/5/2023 Not Ready for Inspection STEVEN BACK
HVAC-Rough 6/5/2023 Corrections Issued STEVEN BACK
PLUMBING-Rough 6/5/2023 Approved STEVEN BACK
Special/Order Compliance 6/5/2023 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 6/14/2023 Approved STEVEN BACK
Green Building Rough 6/14/2023 Approved STEVEN BACK
HVAC-Rough 6/14/2023 Approved STEVEN BACK
Interior/Exterior Lathing 6/14/2023 Partial Approval STEVEN BACK
Insulation 6/23/2023 Conditional Approval DAVID SCANTLIN
Drywall Nailing 6/28/2023 Approved STEVEN BACK
Insulation 6/28/2023 Approved STEVEN BACK
Shower Pan 6/28/2023 Approved STEVEN BACK
Interior/Exterior Lathing 7/3/2023 Approved STEVEN BACK
Special/Order Compliance 7/3/2023 Corrections Issued STEVEN BACK
Final 9/21/2023 Corrections Issued STEVEN BACK
Green Building Final 9/21/2023 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Not Ready STEVEN BACK
Smoke Detectors 9/21/2023 Approved STEVEN BACK
Final 10/5/2023 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/5/2023 SGSOV Approved STEVEN BACK