13411 W CORNELIUS ST 91331
Certificate Information: 13411 W CORNELIUS ST 91331
- Application / Permit
- 23014-20000-00038
- Plan Check / Job No.
- B22VN19244
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT AND ADD TO (E) GARAGE INTO ADUper Ordinance and LAMC 12.22 A33 (c) &(d)
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2023 | ZAW HAN |
| Corrections Issued | 1/17/2023 | ZAW HAN |
| Plan Check Approved | 2/26/2023 | ZAW HAN |
| Issued | 2/28/2023 | APPLICANT |
| CofO in Progress | 9/25/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
| CofO Issued | 10/14/2025 | RUBEN SALAS |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2023 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 1/18/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 1/20/2023 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 1/20/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 1/20/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 1/20/2023 | MEGAN GODINEZ |
| Clean Up Green Up | Cleared | 1/27/2023 | BRENNEN OBETO |
| Hold | Cleared | 7/6/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/12/2023 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 7/12/2023 | Corrections Issued | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 8/8/2023 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/8/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/8/2023 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 8/8/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/30/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2023 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 11/30/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/19/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2024 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 1/19/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/4/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/11/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 3/11/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| MERV13>=Rough | 3/11/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 3/19/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/19/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 3/19/2024 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 3/20/2024 | No Access for Inspection | KEVIN BERBERYAN |
| Drywall Nailing | 5/23/2024 | Corrections Issued | JOHN COLEMAN |
| Insulation | 6/6/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/21/2024 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 8/4/2025 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/20/2025 | Approved | MICHEL ABAJAN |
| Final | 8/20/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 8/20/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 8/20/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 8/20/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 8/20/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 8/20/2025 | Approved | MICHEL ABAJAN |
| Final | 9/23/2025 | OK to Issue CofO | JENNIFER RABUCHIN |