17245 W STAGG ST 91325

Certificate Information: 17245 W STAGG ST 91325

Application / Permit
23014-20000-00015
Plan Check / Job No.
B23VN00025
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' x 20' DETACHED GARAGE TO (N) ADU + 11' x 15' ADDITION PER LAMC 12.22 A.33(c) AND (d). COMPLY WITH DEPARTMENT ORDER effective date 01/19/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 2/8/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2023 APPLICANT
Assigned to Plan Check Engineer 1/6/2023 ISIS ARGUETA
Corrections Issued 1/7/2023 ISIS ARGUETA
Building Plans Picked Up 1/25/2023 APPLICANT
Plan Check Approved 2/8/2023 ALEC MOUSAKHANIAN
Issued 2/8/2023 APPLICANT
CofO in Progress 9/9/2024 MICKEY YAMASHITA
CofO Issued 11/27/2024 DAVID JAMES
Permit Finaled 11/27/2024 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 1/13/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 1/13/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/18/2023 COLIN LOREDO
Sewer availability Cleared 1/18/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/7/2023 Corrections Issued THOMAS WOODS
Sewer 4/10/2023 Approved THOMAS WOODS
Excavation/Setback/Form/Re-Bar 4/18/2023 Not Ready for Inspection LEO MILBAUER
PLUMBING-Rough 4/18/2023 Partial Inspection LEO MILBAUER
Deputy Drilled-In Anchors 4/24/2023 No Result Entered MARSHALL RUMPF
Footing/Foundation/Slab 4/28/2023 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 5/2/2023 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 6/12/2023 Corrections Issued LUCIANO GAUNA
PLUMBING-Rough 6/12/2023 Not Ready for Inspection LUCIANO GAUNA
Wood Frame 6/12/2023 Not Ready for Inspection LUCIANO GAUNA
ELECTRICAL-Rough 6/16/2023 No Access for Inspection LUCIANO GAUNA
PLUMBING-Rough 6/16/2023 No Access for Inspection LUCIANO GAUNA
Wood Frame 6/16/2023 No Access for Inspection LUCIANO GAUNA
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 8/10/2023 Approved MICKEY YAMASHITA
Sewer 8/10/2023 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 8/17/2023 Corrections Issued MICKEY YAMASHITA
Gas Test 8/17/2023 Corrections Issued MICKEY YAMASHITA
Green Building Rough 8/17/2023 Partial Approval MICKEY YAMASHITA
PLUMBING-Rough 8/17/2023 Partial Approval MICKEY YAMASHITA
Sewer 8/17/2023 Corrections Issued MICKEY YAMASHITA
Wood Frame 8/17/2023 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 9/20/2023 Corrections Issued MICKEY YAMASHITA
Gas Test 9/20/2023 Corrections Issued MICKEY YAMASHITA
Interior/Exterior Lathing 9/20/2023 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 10/4/2023 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 10/4/2023 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 10/25/2023 No Access for Inspection MICKEY YAMASHITA
ELECTRICAL-Rough 10/30/2023 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 11/15/2023 Conditional Approval MICKEY YAMASHITA
Sewer 11/15/2023 Corrections Issued MICKEY YAMASHITA
Drywall Nailing 12/13/2023 Approved MICKEY YAMASHITA
ELECTRICAL-Rough 12/13/2023 Approved MICKEY YAMASHITA
Green Building Rough 12/13/2023 Approved MICKEY YAMASHITA
HVAC-Rough 12/13/2023 Conditional Approval MICKEY YAMASHITA
Drywall Nailing 12/18/2023 Approved MICKEY YAMASHITA
Shower Pan 1/23/2024 Corrections Issued MICKEY YAMASHITA
Shower Pan 1/29/2024 Corrections Issued MICKEY YAMASHITA
Sewer 2/12/2024 Not Ready for Inspection MICKEY YAMASHITA
Shower Pan 2/12/2024 Approved MICKEY YAMASHITA
Shower Pan 2/13/2024 Approved MICKEY YAMASHITA
Interior/Exterior Lathing 2/20/2024 Approved MICKEY YAMASHITA
ELECTRICAL-Rough 4/22/2024 Corrections Issued MICKEY YAMASHITA
Sewer 4/22/2024 Approved MICKEY YAMASHITA
BUILDING-Rough-Frame 8/7/2024 Approved MICKEY YAMASHITA
Final 8/7/2024 Corrections Issued MICKEY YAMASHITA
Green Building Final 8/7/2024 Approved MICKEY YAMASHITA
SGSOV-Seismic Gas S/O Valve 8/7/2024 SGSOV Approved MICKEY YAMASHITA
Smoke Detectors 8/7/2024 Approved MICKEY YAMASHITA
ELECTRICAL-Final 8/20/2024 Approved MICKEY YAMASHITA
Final 8/20/2024 Not Ready for Inspection MICKEY YAMASHITA
HVAC-Final 8/20/2024 Approved MICKEY YAMASHITA
PLUMBING-Final 8/20/2024 Conditional Approval MICKEY YAMASHITA
ELECTRICAL-Final 9/9/2024 Approved MICKEY YAMASHITA
Final 9/9/2024 OK to Issue CofO MICKEY YAMASHITA
HVAC-Final 9/9/2024 Approved MICKEY YAMASHITA
PLUMBING-Final 9/9/2024 Approved MICKEY YAMASHITA