9701 N PENFIELD AVE 91311

Certificate Information: 9701 N PENFIELD AVE 91311

Application / Permit
23014-20000-00014
Plan Check / Job No.
B22VN19232
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20'-6" X 54'-3" IRREGULAR -SHAPED ADDITION TO REAR OF SINGLE FAMILY DWELLING TO CREATE ATTACHED RECREATION ROOM WITH LAUNDRY AND REMODEL (3) BATHROOMS AND KITCHEN. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 8/1/2023
Issuing Office
Current Status
Issued on 8/1/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/5/2023 APPLICANT
Assigned to Plan Check Engineer 1/12/2023 GURUNATH NESARAJAH
Corrections Issued 1/12/2023 GURUNATH NESARAJAH
Applicant returned to address corrections 3/16/2023 GURUNATH NESARAJAH
Plan Check Approved 7/31/2023 DANIEL ABRAMYAN
Issued 8/1/2023 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 4/10/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/11/2023 ROMAN GUTIERREZ
Low Impact Development Cleared 6/2/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 6/5/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Rene; Lic. No.: C83330 11027 EL REY DR      WHITTIER, CA 90606

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/18/2023 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 8/18/2023 Partial Approval DAVID SCANTLIN
Deputy Drilled-In Anchors 8/30/2023 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 8/31/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Partial Approval JOHN KIDWELL
Special/Order Compliance 9/27/2023 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Approved DAVID SCANTLIN
Deputy Wood Construction 11/27/2024 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 3/20/2025 Approved DAVID SCANTLIN
ELECTRICAL-Rough 3/20/2025 Approved DAVID SCANTLIN
Gas Test 3/20/2025 Approved DAVID SCANTLIN
Green Building Rough 3/20/2025 Approved DAVID SCANTLIN
HVAC-Rough 3/20/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 3/20/2025 Approved DAVID SCANTLIN
Insulation 5/29/2025 Approved KRISTEN CAUSEY
Shower Pan 5/29/2025 Approved KRISTEN CAUSEY
Drywall Nailing 6/13/2025 Approved JEFFREY HARTLINE
Gas Test 6/13/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 6/13/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Final 3/13/2026 Corrections Issued JACK KARGODORIAN
HVAC-Final 3/13/2026 Approved JACK KARGODORIAN
Pre-Inspection 3/13/2026 Approved JACK KARGODORIAN
Smoke Detectors 3/13/2026 Approved JACK KARGODORIAN
Gas Test 3/17/2026 Approved DAVID SCANTLIN