580 N PASEO MIRAMAR 90272
Certificate Information: 580 N PASEO MIRAMAR 90272
- Application / Permit
- 23014-10002-03395
- Plan Check / Job No.
- B25LA38680
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN SUPPLEMENTAL TO 23014-10000-03395 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY WITH 1 LEVEL BASEMENT, 164'-5"x77'-6". NFPA 13(D) SPRINKLERS THROUGHOUT EO1
- Permit Issued
- Issued on 6/17/2026
- Issuing Office
- Current Status
- Issued on 6/17/2026
Permit Application Status History
| Submitted | 9/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2025 | STARR CHEN |
| Corrections Issued | 9/22/2025 | STARR CHEN |
| Quality Review Completed | 9/24/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 10/10/2025 | STARR CHEN |
| Applicant returned to address corrections | 10/24/2025 | STARR CHEN |
| Applicant returned to address corrections | 11/5/2025 | KEVIN MORALES |
| Applicant returned to address corrections | 2/12/2026 | STARR CHEN |
| Applicant returned to address corrections | 3/11/2026 | STARR CHEN |
| Plan Check Approved | 6/8/2026 | STARR CHEN |
| Issued | 6/17/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 9/25/2025 | CINDY QI |
| Sewer availability | Cleared | 9/25/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 9/30/2025 | LAVEON RIDER |
| Work Adjacent to Public Way | Cleared | 6/8/2026 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Mesh Prime Construction Inc; Lic. No.: 1151510-B | , |
| Engineer | Mirzadeh,, Amir; Lic. No.: C58119 | P O BOX 572110 TARZANA, CA 91357 |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 18823 LA AMISTAD PL TARZANA, CA 91356 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Piling/Pier/Caisson | 8/12/2026 |
Inspection Request History
| Pre-Inspection | 6/22/2026 | Approved | MICHAEL ALLEN |
| Pre-Inspection | 7/2/2026 | Partial Inspection | DANIEL VERA |