1138 S CREST DR 90035

Certificate Information: 1138 S CREST DR 90035

Application / Permit
23014-10002-00805
Plan Check / Job No.
B23LA22622
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Supplemental permit to 23014-10001-00805 to address field revisions. Changes are clouded with delta No.2
Permit Issued
Issued on 12/8/2023
Issuing Office
Current Status
Permit Finaled on 4/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2023 APPLICANT
Assigned to Plan Check Engineer 12/6/2023 WEIJIAN HUANG
Plan Check Approved 12/7/2023 WEIJIAN HUANG
Issued 12/8/2023 APPLICANT
Permit Finaled 4/2/2025 EVAN COOPER

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: NA77737       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/11/2024 No Access for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 1/12/2024 Not Ready for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 1/17/2024 Approved MEL KHACHATOURIAN
Footing/Foundation/Slab 1/17/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 3/7/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 5/7/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 5/7/2024 Partial Approval MEL KHACHATOURIAN
HVAC-Rough 5/7/2024 Corrections Issued MEL KHACHATOURIAN
PLUMBING-Rough 5/7/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 5/17/2024 Partial Approval MEL KHACHATOURIAN
HVAC-Rough 5/17/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 6/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 6/11/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 6/24/2024 Corrections Issued MEL KHACHATOURIAN
Wood Frame 6/24/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 7/16/2024 Partial Approval MEL KHACHATOURIAN
Insulation 7/26/2024 Approved MEL KHACHATOURIAN
Drywall Nailing 8/13/2024 Approved DANIEL VERA
Interior/Exterior Lathing 8/22/2024 Approved DANIEL VERA
Shower Pan 8/22/2024 Approved DANIEL VERA
ELECTRICAL-Final 10/10/2024 Approved MEL KHACHATOURIAN
HVAC-Final 10/10/2024 Corrections Issued MEL KHACHATOURIAN
Service/Power Release 10/10/2024 Not Ready for Inspection MEL KHACHATOURIAN
Service/Power Release 10/23/2024 Approved MICHAEL PELHAM
HVAC-Final 10/24/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Final 10/24/2024 Corrections Issued MEL KHACHATOURIAN
HVAC-Final 10/31/2024 Approved MEL KHACHATOURIAN
PLUMBING-Final 10/31/2024 Not Ready for Inspection MEL KHACHATOURIAN
Gas Test 11/8/2024 Approved MEL KHACHATOURIAN
PLUMBING-Final 12/18/2024 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 12/20/2024 No Access for Inspection MEL KHACHATOURIAN
Reinforced Concrete Frame 1/8/2025 Partial Approval ARAM AVEDISIAN
Final 4/2/2025 Permit Finaled EVAN COOPER
METHANE-Final 4/2/2025 Approved EVAN COOPER
Smoke Detectors 4/2/2025 Approved EVAN COOPER