10816 S WILLOWBROOK AVE 90059

Certificate Information: 10816 S WILLOWBROOK AVE 90059

Application / Permit
23014-10001-05152
Plan Check / Job No.
B24LA23117
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT TO 23014-10000-05152 TO ENLARGE ADDITION AND UPDATE INVENTORY NFPA-13D fire sprinklers thru-out.
Permit Issued
Issued on 12/6/2024
Issuing Office
Metro
Current Status
Permit Finaled on 11/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/17/2024 APPLICANT
Assigned to Plan Check Engineer 9/20/2024 MINA HABILI
Corrections Issued 9/21/2024 MINA HABILI
Building Plans Picked Up 9/26/2024 APPLICANT
Applicant returned to address corrections 11/15/2024 SUNMIN LEE
Plan Check Approved 11/22/2024 CARLOS MONTES
Issued 12/6/2024 APPLICANT
Permit Finaled 11/24/2025 ARTHUR NEGRETE

Permit Application Clearance Information

Metro Rail approval Cleared 10/14/2024 JENNIFER SU
Roof/Waste drainage to street Cleared 10/24/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 10/30/2024 JESSICA OPINION
Sewer availability Cleared 10/30/2024 JESSICA OPINION

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B 9214 MANZANAR AVE      DOWNEY, CA 90240
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/17/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 1/17/2025 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 2/3/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 2/3/2025 Approved ANTHONY EGSON
Insulation 3/26/2025 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 3/28/2025 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/28/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 3/28/2025 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 5/20/2025 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 6/2/2025 No Access for Inspection ANTHONY EGSON
ELECTRICAL-Rough 6/2/2025 No Access for Inspection ANTHONY EGSON
Green Building Rough 6/2/2025 No Access for Inspection ANTHONY EGSON
HVAC-Rough 6/2/2025 No Access for Inspection ANTHONY EGSON
PLUMBING-Rough 6/2/2025 No Access for Inspection ANTHONY EGSON
Rough-Elec/Plmb/HVAC 6/3/2025 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 7/10/2025 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 7/10/2025 Approved JOSEPH MCGARRY
HVAC-Rough 7/10/2025 Conditional Approval JOSEPH MCGARRY
PLUMBING-Rough 7/10/2025 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 7/10/2025 Approved JOSEPH MCGARRY
Insulation 7/14/2025 Approved JOHN KLARIN
Drywall Nailing 7/23/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 7/23/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 11/14/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 11/14/2025 Corrections Issued ANTHONY EGSON
Final 11/14/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Final 11/14/2025 Approved ANTHONY EGSON
Green Building Rough 11/14/2025 Approved ANTHONY EGSON
HVAC-Final 11/14/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Final 11/14/2025 Corrections Issued ANTHONY EGSON
Service/Power Release 11/14/2025 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 11/14/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 11/24/2025 Approved ARTHUR NEGRETE
Final 11/24/2025 Permit Finaled ARTHUR NEGRETE
HVAC-Final 11/24/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 11/24/2025 Approved ARTHUR NEGRETE
Service/Power Release 11/24/2025 Approved ARTHUR NEGRETE
Smoke Detectors 11/24/2025 Approved ARTHUR NEGRETE