1027 S TREMAINE AVE 90019
Certificate Information: 1027 S TREMAINE AVE 90019
- Application / Permit
- 23014-10001-03394
- Plan Check / Job No.
- B24LA02098
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPLIMENTAL TO PERMIT #23014-10000-03394 TO REVISE THE SCOPE OF WORK TO CONVERSION OF EXISTING GARAGE TO AN ACCESSORY DWELLING UNIT PER CA STATE GOVERNMENT CODE SECTION 65852.2(d)(2). EXISTING CONSTRUCTION DOES NOT POSE A THREAT TO THE PUBLIC'S HEALTH AND SAFETY.
- Permit Issued
- Issued on 3/27/2024
- Issuing Office
- Current Status
- CofO Issued on 12/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | TSE MING HUANG |
| Corrections Issued | 2/26/2024 | TSE MING HUANG |
| Quality Review Completed | 2/26/2024 | EUGENE BARBEAU |
| Assigned to Zoning Architect | 2/28/2024 | TSE MING HUANG |
| Plan Check Approved | 3/26/2024 | TSE MING HUANG |
| Issued | 3/27/2024 | APPLICANT |
| Permit Finaled-Status Void | 10/10/2024 | ENRIQUE MIRELES |
| Re-Activate Permit | 11/14/2024 | ENRIQUE MIRELES |
| CofO in Progress | 12/26/2024 | JOAQUIN GREENOUGH |
| Permit Finaled | 12/26/2024 | DEROLD HAUFF |
| CofO Issued | 12/26/2024 | DEROLD HAUFF |
| Permit Finaled | 12/26/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/28/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 2/28/2024 | WALTER RAMIREZ |
| Address approval | Cleared | 3/5/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 3/5/2024 | CHRISTINA BRACO |
| CPC | Cleared | 3/13/2024 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2024 | CHRISTINA BRACO |
Contact Information
| Architect | Gaudio,, Kristin Drews; Lic. No.: NA35634 | , |
| Contractor | Rebuilt Homes Inc; Lic. No.: 1063540-B | , |
| Contractor | Rebuilt; Lic. No.: 1063540-B | , |
| Engineer | Saleh,, Zouheir Toufic; Lic. No.: C42881 | 1304 CORTE MALTERA COSTA MESA, CA 92626 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/1/2024 | No Access for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 4/1/2024 | No Access for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/3/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 4/3/2024 | Partial Approval | CRAIG DAVIS |
| HVAC-Rough | 4/3/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 4/3/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 4/10/2024 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 4/10/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 4/10/2024 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 4/12/2024 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/16/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 4/16/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 6/5/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 6/5/2024 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 6/5/2024 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2024 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/11/2024 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Approved | JOSEPH MCGARRY |
| Sewer | 6/21/2024 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 7/1/2024 | Approved | RONNIE MINDANAO |
| Insulation | 7/3/2024 | Conditional Approval | RONNIE MINDANAO |
| Drywall Nailing | 7/9/2024 | Conditional Approval | RONNIE MINDANAO |
| Interior/Exterior Lathing | 7/29/2024 | Approved | RONNIE MINDANAO |
| Shower Pan | 7/29/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 7/31/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 8/2/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/3/2024 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 10/3/2024 | Corrections Issued | RONNIE MINDANAO |
| Smoke Detectors | 10/3/2024 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 10/8/2024 | Approved | RONNIE MINDANAO |
| Final | 10/8/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 10/8/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 10/10/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 10/10/2024 | Approved | ENRIQUE MIRELES |
| Final | 11/15/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 12/26/2024 | OK to Issue CofO | JOAQUIN GREENOUGH |