1950 N CUMMINGS DR 90027
Certificate Information: 1950 N CUMMINGS DR 90027
- Application / Permit
- 23014-10001-01137
- Plan Check / Job No.
- B24LA02614
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN SUPPLEMENTAL TO 23014-10000-01137 TO REVISED POOL LOCATION
- Permit Issued
- Issued on 4/24/2024
- Issuing Office
- Current Status
- Issued on 4/24/2024
Permit Application Status History
| Submitted | 2/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | JAD BASMA |
| Corrections Issued | 2/24/2024 | JAD BASMA |
| Quality Review Completed | 2/27/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 3/14/2024 | JAD BASMA |
| Plan Check Approved | 4/23/2024 | JAD BASMA |
| Issued | 4/24/2024 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/4/2024 | Approved | ROY SPAULDING |
| Deputy Other (see comments) | 6/28/2024 | Conditional Approval | ROY SPAULDING |
| Deputy Shotcrete | 7/2/2024 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 7/11/2024 | Approved | ROY SPAULDING |
| Deputy Other (see comments) | 7/15/2024 | Conditional Approval | ROY SPAULDING |
| Pre-Gunite | 9/25/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Gunite | 9/30/2024 | Approved | CRAIG VAUGHAN |
| Deputy Shotcrete | 10/4/2024 | Conditional Approval | CRAIG VAUGHAN |
| Deputy Shotcrete | 10/10/2024 | Conditional Approval | BRENDAN MORELLI |
| Grounding or Bonding | 10/10/2024 | Partial Approval | BRENDAN MORELLI |
| Deck | 10/30/2024 | Approved | CRAIG VAUGHAN |
| Deputy Shotcrete | 2/20/2025 | Conditional Approval | CRAIG VAUGHAN |
| Enclosure/Fence | 5/29/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 7/23/2025 | Corrections Issued | CRAIG VAUGHAN |
| Gas Piping or Gas Test | 7/24/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Piping or Gas Test | 7/30/2025 | Approved | CRAIG VAUGHAN |
| Final | 9/23/2025 | Conditional Approval | CRAIG VAUGHAN |
| Green Building Final | 9/23/2025 | Approved | CRAIG VAUGHAN |
| Final | 9/29/2025 | Corrections Issued | CRAIG VAUGHAN |