4212 S TIVOLI AVE 90066
Certificate Information: 4212 S TIVOLI AVE 90066
- Application / Permit
- 23014-10000-05402
- Plan Check / Job No.
- B23LA24565
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Conversion and addition to existing detached garage to A.D.U. per LAMC 12.22 A.33 (c)-(d). Design per licensed engineer.
- Permit Issued
- Issued on 9/6/2024
- Issuing Office
- Current Status
- CofO Issued on 3/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2024 | ALEXANDER JOO |
| Corrections Issued | 1/11/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 3/28/2024 | CAROLEAN BASMA |
| Plan Check Approved | 4/2/2024 | CAROLEAN BASMA |
| Issued | 9/6/2024 | APPLICANT |
| CofO in Progress | 2/25/2026 | ANTHONY EGSON |
| Permit Finaled | 3/3/2026 | RICHARD STEINBACH |
| CofO Issued | 3/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/29/2024 | ALESSANDRO MERCURI |
| Address approval | Cleared | 1/30/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 1/30/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2024 | DARIN LAM |
| Sewer availability | Cleared | 1/31/2024 | DARIN LAM |
| Construction near power lines | Cleared | 3/27/2024 | EDGAR PASCUA |
Contact Information
| Contractor | Bela Remodeling; Lic. No.: 1038287-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/20/2024 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 12/20/2024 | Partial Inspection | JAYLIN GRAVITTE |
| Footing/Foundation/Slab | 12/26/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Corrections Issued | JESUS PINEDA |
| Underground Mechanical | 1/21/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 1/27/2025 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 1/30/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 1/30/2025 | Corrections Issued | JESUS PINEDA |
| Gas Test | 2/4/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 2/4/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 2/26/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 2/26/2025 | Corrections Issued | JESUS PINEDA |
| Underground Mechanical | 2/26/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 3/5/2025 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 4/4/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 4/4/2025 | Approved | MICHAEL ALLEN |
| Insulation | 5/12/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Drywall Nailing | 5/22/2025 | Approved | JAYLIN GRAVITTE |
| Insulation | 5/22/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 5/22/2025 | Approved | JAYLIN GRAVITTE |
| Smoke Detectors | 5/22/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 6/3/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/28/2026 | Corrections Issued | MICHAEL ALLEN |
| Final | 1/28/2026 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 1/28/2026 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Final | 1/28/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Not Ready | MICHAEL ALLEN |
| Smoke Detectors | 1/28/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 2/11/2026 | SGSOV Not Ready | MICHAEL ALLEN |
| Pre-Inspection | 2/17/2026 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 2/24/2026 | Approved | ANTHONY EGSON |
| Final | 2/24/2026 | OK to Issue CofO | ANTHONY EGSON |
| HVAC-Final | 2/24/2026 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Approved | ANTHONY EGSON |