1915 1/2 S WEST VIEW ST 90016
Certificate Information: 1915 1/2 S WEST VIEW ST 90016
- Application / Permit
- 23014-10000-05391
- Plan Check / Job No.
- B23LA24548
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) 14'-2" X 18'-1" DETACHED GARAGE AND ADD 16'-1" X 17'-8" 2ND FLOOR TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/4/2024
- Issuing Office
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | RAPHAEL ROSAS |
| Corrections Issued | 1/30/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 2/9/2024 | STEVEN KIM |
| Applicant returned to address corrections | 8/19/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/3/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/11/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 9/19/2024 | RAPHAEL ROSAS |
| Issued | 10/4/2024 | APPLICANT |
| CofO in Progress | 9/8/2025 | JUSTIN HAWLEY |
| Permit Finaled | 9/9/2025 | DEROLD HAUFF |
| CofO Issued | 9/9/2025 | DEROLD HAUFF |
| Permit Finaled | 9/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2024 | KEVIN AVILA |
| Roof/Waste drainage to street | Cleared | 3/19/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 3/21/2024 | AMBER CAMPBELL |
| Construction near power lines | Cleared | 5/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: NA91046 | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/25/2024 | Approved | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 12/13/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/13/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 2/6/2025 | Conditional Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 3/6/2025 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 3/6/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 3/6/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Sewer | 3/6/2025 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 3/6/2025 | Partial Inspection | ALEX COLIN |
| Excavation/Setback/Form/Re-Bar | 3/11/2025 | Approved | ARTHUR NEGRETE |
| Reinforced Masonry Frame | 3/11/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 4/30/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 4/30/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 4/30/2025 | Approved | ARTHUR NEGRETE |
| Wood Frame | 4/30/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 5/20/2025 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 5/22/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 5/22/2025 | Approved | ARTHUR NEGRETE |
| Wood Frame | 5/22/2025 | Partial Approval | ARTHUR NEGRETE |
| Insulation | 5/27/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 6/10/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Shower Pan | 6/10/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 6/12/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/12/2025 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 6/20/2025 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 8/29/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 8/29/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Final | 8/29/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 8/29/2025 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Not Required | WILLIAM SIERRA |
| Smoke Detectors | 8/29/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Final | 9/3/2025 | Approved | JUSTIN HAWLEY |
| Final | 9/3/2025 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Final | 9/3/2025 | Approved | JUSTIN HAWLEY |
| Smoke Detectors | 9/3/2025 | Approved | JUSTIN HAWLEY |
| Final | 9/8/2025 | OK to Issue CofO | JUSTIN HAWLEY |