1915 1/2 S WEST VIEW ST 90016

Certificate Information: 1915 1/2 S WEST VIEW ST 90016

Application / Permit
23014-10000-05391
Plan Check / Job No.
B23LA24548
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) 14'-2" X 18'-1" DETACHED GARAGE AND ADD 16'-1" X 17'-8" 2ND FLOOR TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/4/2024
Issuing Office
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 RAPHAEL ROSAS
Corrections Issued 1/30/2024 RAPHAEL ROSAS
Quality Review Completed 2/9/2024 STEVEN KIM
Applicant returned to address corrections 8/19/2024 RAPHAEL ROSAS
Applicant returned to address corrections 9/3/2024 RAPHAEL ROSAS
Applicant returned to address corrections 9/11/2024 RAPHAEL ROSAS
Plan Check Approved 9/19/2024 RAPHAEL ROSAS
Issued 10/4/2024 APPLICANT
CofO in Progress 9/8/2025 JUSTIN HAWLEY
Permit Finaled 9/9/2025 DEROLD HAUFF
CofO Issued 9/9/2025 DEROLD HAUFF
Permit Finaled 9/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/9/2024 KEVIN AVILA
Roof/Waste drainage to street Cleared 3/19/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 3/21/2024 AMBER CAMPBELL
Sewer availability Cleared 3/21/2024 AMBER CAMPBELL
Construction near power lines Cleared 5/9/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: NA91046       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/25/2024 Approved JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 12/13/2024 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/13/2024 Corrections Issued JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 2/6/2025 Conditional Approval JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 3/6/2025 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 3/6/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 3/6/2025 Not Ready for Inspection ARTHUR NEGRETE
Sewer 3/6/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/6/2025 Partial Inspection ALEX COLIN
Excavation/Setback/Form/Re-Bar 3/11/2025 Approved ARTHUR NEGRETE
Reinforced Masonry Frame 3/11/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 4/30/2025 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Rough 4/30/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 4/30/2025 Approved ARTHUR NEGRETE
Wood Frame 4/30/2025 Approved ARTHUR NEGRETE
HVAC-Rough 5/20/2025 Corrections Issued RONNIE MINDANAO
BUILDING-Rough-Frame 5/22/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Approved ARTHUR NEGRETE
HVAC-Rough 5/22/2025 Approved ARTHUR NEGRETE
Wood Frame 5/22/2025 Partial Approval ARTHUR NEGRETE
Insulation 5/27/2025 Approved ALEX COLIN
Drywall Nailing 6/10/2025 Not Ready for Inspection JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Not Ready for Inspection JUSTIN HAWLEY
Shower Pan 6/10/2025 Approved JUSTIN HAWLEY
Green Building Rough 6/12/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 6/12/2025 Approved JUSTIN HAWLEY
Drywall Nailing 6/20/2025 Approved JUSTIN HAWLEY
ELECTRICAL-Final 8/29/2025 Corrections Issued WILLIAM SIERRA
Final 8/29/2025 Corrections Issued WILLIAM SIERRA
HVAC-Final 8/29/2025 Approved WILLIAM SIERRA
PLUMBING-Final 8/29/2025 Corrections Issued WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Not Required WILLIAM SIERRA
Smoke Detectors 8/29/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Final 9/3/2025 Approved JUSTIN HAWLEY
Final 9/3/2025 Corrections Issued JUSTIN HAWLEY
PLUMBING-Final 9/3/2025 Approved JUSTIN HAWLEY
Smoke Detectors 9/3/2025 Approved JUSTIN HAWLEY
Final 9/8/2025 OK to Issue CofO JUSTIN HAWLEY