5606-5606 1/2 E BALTIMORE ST 90042
Certificate Information: 5606-5606 1/2 E BALTIMORE ST 90042
- Application / Permit
- 23014-10000-05373
- Plan Check / Job No.
- B23LA24517
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 162SF (E) ATTACHED GARAGE AND 246SF PORTION OF SFD WITH AN ADDITION OF 300SF TO AN ATTACHED ADU TOTALING 708SF AT THE REAR PER LAMC 12.22 A.33(C) AND (E).
- Permit Issued
- Issued on 4/3/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2024 | DAVID CASTILLO |
| Corrections Issued | 1/5/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 1/18/2024 | JAD BASMA |
| Applicant returned to address corrections | 2/7/2024 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 2/29/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 3/28/2024 | ALEXANDER JOO |
| Plan Check Approved | 4/3/2024 | ALEXANDER JOO |
| Issued | 4/3/2024 | APPLICANT |
| CofO in Progress | 4/23/2025 | DAVID WILLIAMS |
| Permit Finaled | 4/23/2025 | DEROLD HAUFF |
| CofO Issued | 4/23/2025 | DEROLD HAUFF |
| Permit Finaled | 4/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2024 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2024 | ARNULFO CHAMU |
| Sewer availability | Cleared | 1/10/2024 | ARNULFO CHAMU |
| Grading Pre-Inspection | Cleared | 1/16/2024 | SERGIO VALENZUELA |
| HPOZ | Cleared | 2/21/2024 | MICAELA TORRES-GIL |
| Low Impact Development (LID) | Cleared | 3/15/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/26/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Builder 20; Lic. No.: 1023066-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/25/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 4/26/2024 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 5/3/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/1/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/20/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/20/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/27/2024 | Partial Approval | BRENDAN MORELLI |
| Insulation | 8/30/2024 | Corrections Issued | LUIS CASTRO |
| Drywall Nailing | 10/2/2024 | Partial Approval | ROY SPAULDING |
| Interior/Exterior Lathing | 10/16/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Shower Pan | 10/21/2024 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 12/3/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 12/24/2024 | Corrections Issued | CRAIG DAVIS |
| Gas Test | 12/24/2024 | Approved | CRAIG DAVIS |
| Pre-Inspection | 1/13/2025 | Partial Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/13/2025 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Final | 2/13/2025 | Partial Approval | CRAIG DAVIS |
| Final | 2/13/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 2/13/2025 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 2/13/2025 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 2/13/2025 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 2/13/2025 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/13/2025 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 2/13/2025 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 4/7/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 4/7/2025 | Approved | DAVID WILLIAMS |
| Final | 4/7/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 4/7/2025 | Approved | DAVID WILLIAMS |
| Green Building Final | 4/7/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 4/7/2025 | Approved | DAVID WILLIAMS |
| Final | 4/14/2025 | No Access for Inspection | DAVID WILLIAMS |
| Final | 4/16/2025 | Corrections Issued | DAVID WILLIAMS |
| Service/Power Release | 4/17/2025 | Approved | DAVID WILLIAMS |
| Final | 4/23/2025 | OK to Issue CofO | DAVID WILLIAMS |