3001-3030 N HUTTON PL 90210

Certificate Information: 3001-3030 N HUTTON PL 90210

Application / Permit
23014-10000-05370
Plan Check / Job No.
B23LA24509
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ATTACHED ADU, 1 CAR GARAGE, STORAGE ROOM, AND BATHROOM. ADU PER LAMC 12.22 A.33 (c) and (e).
Permit Issued
Issued on 4/30/2024
Issuing Office
Valley
Current Status
Issued on 4/30/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/29/2023 APPLICANT
Assigned to Plan Check Engineer 1/4/2024 MARCELA FRANQUEZ
Corrections Issued 1/6/2024 MARCELA FRANQUEZ
Quality Review Completed 1/10/2024 KEN GILL
Building Plans Picked Up 1/12/2024 APPLICANT
Plan Check Approved 4/24/2024 MARCELA FRANQUEZ
Issued 4/30/2024 APPLICANT

Permit Application Clearance Information

GPI Written Notices Cleared 1/8/2024 MARCELA FRANQUEZ
Grading Pre-Inspection Cleared 1/8/2024 MARCELA FRANQUEZ
ZI Cleared 1/11/2024 ASHLEY RODARTE
BHO/Hillside ordinance Cleared 1/12/2024 DINAH GARIN
BHO/Hillside ordinance Cleared 1/12/2024 DINAH GARIN
BHO/Hillside ordinance Cleared 1/12/2024 DINAH GARIN
BHO/Hillside ordinance Cleared 1/12/2024 DINAH GARIN
BHO/Hillside ordinance Cleared 1/12/2024 DINAH GARIN
Address approval Cleared 1/19/2024 DINAH GARIN
Permit Cleared 1/19/2024 DINAH GARIN
Sewer availability Cleared 1/19/2024 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/22/2024 DINAH GARIN
Watercourse Cleared 1/23/2024 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 2/15/2024 MATTHEW CRAIG
Trees in Parkway Cleared 3/18/2024 ADALBERTO VERA
Low Impact Development (LID) Cleared 4/4/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 4/5/2024 DINAH GARIN
Specific Plan Cleared 4/11/2024 TIFFANY CORRALES

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/14/2024 Approved SEAN HAUPT
Footing/Foundation/Slab 5/31/2024 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 6/17/2024 Approved SEAN HAUPT
Footing/Foundation/Slab 6/17/2024 Approved SEAN HAUPT
Special/Order Compliance 6/17/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 10/25/2024 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 4/1/2025 Corrections Issued SEAN HAUPT
Special/Order Compliance 4/1/2025 Approved SEAN HAUPT
BUILDING-Rough-Frame 6/20/2025 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 6/20/2025 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 12/5/2025 Partial Approval SEAN HAUPT
HVAC-Rough 12/17/2025 Corrections Issued CARLOS MATAMOROS
Interior/Exterior Lathing 1/9/2026 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 1/21/2026 Corrections Issued CARLOS MATAMOROS
Interior/Exterior Lathing 5/11/2026 Corrections Issued CARLOS MATAMOROS
Interior/Exterior Lathing 5/20/2026 Approved CARLOS MATAMOROS
Gas Test 6/2/2026 Approved CARLOS MATAMOROS
PLUMBING-Rough 6/2/2026 Approved CARLOS MATAMOROS
Special/Order Compliance 6/2/2026 Corrections Issued CARLOS MATAMOROS