1467-1471 W BROWNING BLVD 90062
Certificate Information: 1467-1471 W BROWNING BLVD 90062
- Application / Permit
- 23014-10000-05361
- Plan Check / Job No.
- B23LA24490
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- MAJOR REMODEL AND ADDITION TO (E) DUPLEX (1-STORY) TO BECOME A 4-STORY DUPLEX WITH ATTACHED ADU PER ORDINANCE LAMC 12.22 A.33(c) and (e) NFPA 13R SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 2/14/2025
- Issuing Office
- Metro
- Current Status
- Issued on 2/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | JAD BASMA |
| Corrections Issued | 1/7/2024 | JAD BASMA |
| Quality Review Completed | 1/10/2024 | KEN GILL |
| Building Plans Picked Up | 2/21/2024 | APPLICANT |
| Plan Check Approved | 1/9/2025 | JAD BASMA |
| Issued | 2/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/19/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 2/2/2024 | AMBER CAMPBELL |
| Low Impact Development (LID) | Cleared | 3/15/2024 | PATRICK LOPEZ |
| Hydrant and Access approval | Cleared | 3/18/2024 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 3/18/2024 | JUSTIN BICOL |
| Frnt yard landscape/Water mgmt | Cleared | 4/3/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 4/3/2024 | DANIEL CORONADO |
| Tenant Habitability Plan | Cleared | 1/9/2025 | JUAN ACOSTA |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/1/2025 | Conditional Approval | SABAS ALONSO |
| Deputy Other (see comments) | 5/1/2025 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/8/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/27/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Insulation | 5/27/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 5/29/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 10/30/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 10/30/2025 | Corrections Issued | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 10/31/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 10/31/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 10/31/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/5/2025 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 11/5/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 11/5/2025 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/7/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 11/7/2025 | Approved | SABAS ALONSO |
| Insulation | 11/17/2025 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 12/11/2025 | Approved | SABAS ALONSO |
| Insulation | 12/11/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/11/2025 | Approved | SABAS ALONSO |
| Sewer | 5/27/2026 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/27/2026 | Approved | SABAS ALONSO |