1467-1471 W BROWNING BLVD 90062

Certificate Information: 1467-1471 W BROWNING BLVD 90062

Application / Permit
23014-10000-05361
Plan Check / Job No.
B23LA24490
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
MAJOR REMODEL AND ADDITION TO (E) DUPLEX (1-STORY) TO BECOME A 4-STORY DUPLEX WITH ATTACHED ADU PER ORDINANCE LAMC 12.22 A.33(c) and (e) NFPA 13R SPRINKLERED THROUGH OUT
Permit Issued
Issued on 2/14/2025
Issuing Office
Metro
Current Status
Issued on 2/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/28/2023 APPLICANT
Assigned to Plan Check Engineer 1/4/2024 JAD BASMA
Corrections Issued 1/7/2024 JAD BASMA
Quality Review Completed 1/10/2024 KEN GILL
Building Plans Picked Up 2/21/2024 APPLICANT
Plan Check Approved 1/9/2025 JAD BASMA
Issued 2/14/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/19/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/2/2024 AMBER CAMPBELL
Sewer availability Cleared 2/2/2024 AMBER CAMPBELL
Low Impact Development (LID) Cleared 3/15/2024 PATRICK LOPEZ
Hydrant and Access approval Cleared 3/18/2024 KURT CORRAL
Roof/Waste drainage to street Cleared 3/18/2024 JUSTIN BICOL
Frnt yard landscape/Water mgmt Cleared 4/3/2024 DANIEL CORONADO
ZA Case Cleared 4/3/2024 DANIEL CORONADO
Tenant Habitability Plan Cleared 1/9/2025 JUAN ACOSTA

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/1/2025 Conditional Approval SABAS ALONSO
Deputy Other (see comments) 5/1/2025 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 5/8/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 5/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 5/27/2025 Not Ready for Inspection ALEJANDRO DE ARTOLA
Insulation 5/27/2025 Not Ready for Inspection ALEJANDRO DE ARTOLA
Underground Mechanical 5/27/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval LUIS CASTRO
Insulation 5/29/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/24/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/9/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/28/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 10/30/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 10/30/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 10/31/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 10/31/2025 Approved SABAS ALONSO
PLUMBING-Rough 10/31/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/5/2025 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 11/5/2025 Approved SABAS ALONSO
Green Building Rough 11/5/2025 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 11/7/2025 Approved SABAS ALONSO
Green Building Rough 11/7/2025 Approved SABAS ALONSO
Insulation 11/17/2025 Corrections Issued SABAS ALONSO
Drywall Nailing 12/11/2025 Approved SABAS ALONSO
Insulation 12/11/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 12/11/2025 Approved SABAS ALONSO
Sewer 5/27/2026 Approved SABAS ALONSO
Underground Mechanical 5/27/2026 Approved SABAS ALONSO