238 S LORRAINE BLVD 90004
Certificate Information: 238 S LORRAINE BLVD 90004
- Application / Permit
- 23014-10000-05318
- Plan Check / Job No.
- B23LA24294
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: REMODEL AND ADDITION TO EXISTING SFD 1st Floor Family Room addition = 91 SF Covered Patio Addition = 195 SF Master Suite addition = 244 SF
- Permit Issued
- Issued on 12/16/2024
- Issuing Office
- Current Status
- CofO Issued on 5/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/18/2024 | CRYSTEL MAALOUF |
| Corrections Issued | 1/24/2024 | CRYSTEL MAALOUF |
| Quality Review Completed | 2/5/2024 | YOUNG KIM |
| Applicant returned to address corrections | 4/17/2024 | CRYSTEL MAALOUF |
| Plan Check Approved | 4/22/2024 | CRYSTEL MAALOUF |
| Issued | 12/16/2024 | APPLICANT |
| CofO in Progress | 5/20/2026 | JEFFREY MEAD |
| CofO Issued | 5/21/2026 | DEROLD HAUFF |
| Permit Finaled | 5/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/22/2024 | CELINA MORENO |
| Sewer availability | Cleared | 3/22/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/27/2024 | JEANIE LAM |
| CPC | Cleared | 4/1/2024 | DAMIAN GATTO |
| CPC | Cleared | 4/1/2024 | DAMIAN GATTO |
| CPC | Cleared | 4/1/2024 | DAMIAN GATTO |
| HPOZ | Cleared | 4/1/2024 | DAMIAN GATTO |
| Miscellaneous | Cleared | 4/1/2024 | DAMIAN GATTO |
| Miscellaneous | Cleared | 4/1/2024 | DAMIAN GATTO |
| ZI | Cleared | 4/1/2024 | DAMIAN GATTO |
Contact Information
| Architect | Keener,, Jane Kim; Lic. No.: NA31396 | , |
| Contractor | Lannen Construction Inc; Lic. No.: 811038-B | , |
| Engineer | Howe,, Carl William; Lic. No.: C44773 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
| Engineer | Howe,, Carl William; Lic. No.: NA44773 | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/24/2025 | Partial Approval | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 5/5/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 5/5/2025 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 5/22/2025 | Approved | JEFFREY MEAD |
| Deputy Steel/Welding | 6/4/2025 | Conditional Approval | JEFFREY MEAD |
| Deputy Steel/Welding | 6/6/2025 | Conditional Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Approved | ARTHUR NEGRETE |
| Deputy Wood Construction | 8/8/2025 | Conditional Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Partial Approval | JOSH MEISTER |
| Special/Order Compliance | 8/12/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/10/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 9/10/2025 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 9/10/2025 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 9/12/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 9/12/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/23/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2025 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 9/23/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 9/25/2025 | Approved | GEM DE OCAMPO |
| Deputy Wood Construction | 9/29/2025 | Conditional Approval | JEFFREY MEAD |
| Insulation | 10/6/2025 | Approved | JEFFREY MEAD |
| Shower Pan | 10/10/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 10/22/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 10/30/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 3/2/2026 | Approved | JEFFREY MEAD |
| Gas Test | 4/1/2026 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 4/17/2026 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 5/1/2026 | Approved | JEFFREY MEAD |
| Final | 5/1/2026 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 5/1/2026 | Approved | JEFFREY MEAD |
| HVAC-Final | 5/1/2026 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 5/1/2026 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 5/1/2026 | Approved | JEFFREY MEAD |
| Final | 5/7/2026 | OK to Issue CofO | JEFFREY MEAD |