10602 S ANZAC AVE 90002
Certificate Information: 10602 S ANZAC AVE 90002
- Application / Permit
- 23014-10000-05317
- Plan Check / Job No.
- B23LA24292
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. (N) Addition to rear of (E) SFD. Remodel (E) SFD, scope of work to include: relocate kitchen, bathroom and bedroom per wfpp
- Permit Issued
- Issued on 2/14/2024
- Issuing Office
- Current Status
- Issued on 2/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2024 | AMY GUEVARRA |
| Corrections Issued | 1/11/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 1/31/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 2/5/2024 | JOHNPAUL ISIP |
| Issued | 2/14/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/17/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 1/24/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Ebenezer Construction; Lic. No.: 657529-B | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/8/2024 | Conditional Approval | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 4/10/2024 | Approved | BEN MOLSTAD |
| Footing/Foundation/Slab | 4/10/2024 | Approved | BEN MOLSTAD |
| Sewer | 4/22/2024 | No Access for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 4/25/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 5/1/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 5/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/28/2024 | Partial Approval | BEN MOLSTAD |
| PLUMBING-Rough | 5/28/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 6/7/2024 | Corrections Issued | JAMES CHAVEZ |
| Gas Test | 6/7/2024 | Partial Approval | JAMES CHAVEZ |
| Green Building Rough | 6/7/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Rough | 6/7/2024 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 6/7/2024 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/12/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 6/12/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 6/12/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 6/18/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 6/18/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 6/18/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 6/18/2024 | Partial Approval | BEN MOLSTAD |
| Wood Frame | 6/18/2024 | Approved | BEN MOLSTAD |
| Insulation | 6/24/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 7/5/2024 | Approved | ANSON MAGLASANG |
| Final | 8/27/2024 | Corrections Issued | BARRY HACHE |
| Green Building Final | 8/27/2024 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 8/27/2024 | Approved | BARRY HACHE |
| Special/Order Compliance | 8/27/2024 | Partial Inspection | BEN MOLSTAD |
| Pre-Inspection | 8/30/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 9/27/2024 | No Access for Inspection | BARRY HACHE |
| Green Building Final | 9/27/2024 | No Access for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 10/28/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 10/28/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 10/28/2024 | Approved | ANTHONY EGSON |
| HVAC-Final | 10/28/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 10/28/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 11/25/2024 | No Access for Inspection | ANTHONY EGSON |
| HVAC-Final | 11/25/2024 | No Access for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 12/30/2024 | Approved | ANTHONY EGSON |
| HVAC-Final | 12/30/2024 | Corrections Issued | ANTHONY EGSON |