12401 W SARAH ST 91604

Certificate Information: 12401 W SARAH ST 91604

Application / Permit
23014-10000-05316
Plan Check / Job No.
B23LA24290
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
* * ePlan * * Interior remodel and Rear addition to (E) Single Family Dwelling
Permit Issued
Issued on 1/21/2024
Issuing Office
Current Status
CofO Issued on 10/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2023 APPLICANT
Assigned to Plan Check Engineer 12/29/2023 EDWIN ESPIN
Corrections Issued 12/31/2023 EDWIN ESPIN
Plan Check Approved 1/17/2024 EDWIN ESPIN
Issued 1/21/2024 APPLICANT
CofO in Progress 9/18/2025 CHRISTOPHE COCHRAN
Permit Finaled 10/8/2025 RUBEN SALAS
CofO Issued 10/8/2025 RUBEN SALAS
Permit Finaled 10/8/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/8/2024 RYAN KIM
Roof/Waste drainage to street Cleared 1/8/2024 RYAN KIM
Sewer availability Cleared 1/8/2024 RYAN KIM
ZI Cleared 1/8/2024 ANNA VIDAL

Contact Information

Contractor J M Construction; Lic. No.: 772804-B       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/3/2024 Approved JOHN COLEMAN
Deputy Drilled-In Anchors 4/9/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/10/2024 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 4/15/2024 Corrections Issued CHRISTOPHE COCHRAN
Piling/Pier/Caisson 4/17/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/19/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 6/3/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 6/3/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Rough 6/3/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/17/2024 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 6/17/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/25/2024 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Rough 7/25/2024 Approved CHRISTOPHE COCHRAN
Wood Frame 7/25/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/30/2024 Approved CHRISTOPHE COCHRAN
Insulation 7/30/2024 Approved CHRISTOPHE COCHRAN
Drywall Nailing 8/28/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/28/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 8/28/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/28/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 5/28/2025 Approved CHRISTOPHE COCHRAN
MERV13>=Rough 5/28/2025 Approved CHRISTOPHE COCHRAN
Final 6/4/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 9/10/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 9/10/2025 Approved CHRISTOPHE COCHRAN
MERV13>=Final 9/10/2025 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 9/10/2025 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 9/10/2025 Approved CHRISTOPHE COCHRAN
Final 9/16/2025 OK to Issue CofO CHRISTOPHE COCHRAN