5552 W 82ND ST 90045
Certificate Information: 5552 W 82ND ST 90045
- Application / Permit
- 23014-10000-05305
- Plan Check / Job No.
- B23LA24278
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: HABITABLE SPACE AND COVERED PORCH ADDITION TO (E) SFD
- Permit Issued
- Issued on 7/9/2025
- Issuing Office
- Current Status
- Issued on 7/9/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2024 | JOHNPAUL ISIP |
| Corrections Issued | 1/15/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 5/1/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 2/6/2025 | PINANK PATEL |
| Applicant returned to address corrections | 3/20/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 4/1/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 6/2/2025 | NAREG ATARIAN |
| Plan Check Approved | 6/8/2025 | GURUNATH NESARAJAH |
| No Progress | 6/17/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 6/17/2025 | GURUNATH NESARAJAH |
| No Progress | 6/17/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 6/17/2025 | GURUNATH NESARAJAH |
| Issued | 7/9/2025 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/1/2024 | DARIN LAM |
| ZA Case | Cleared | 5/10/2024 | DANIEL CORONADO |
| Low Impact Development (LID) | Cleared | 1/14/2025 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/15/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2025 | DARIN LAM |
| Specific Plan | Cleared | 1/27/2025 | RICHARD WOO |
| GPI Written Notices | Cleared | 3/20/2025 | AL GAMBLE |
Contact Information
| Architect | Grist,, John Kenneth; Lic. No.: C4295 | 470 STANFORD DRIVE CLAREMONT, CA 91711 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/3/2025 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 11/5/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 3/23/2026 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2026 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 3/23/2026 | Approved | JESUS PINEDA |
| Deputy Wood Construction | 3/25/2026 | Conditional Approval | DAVID FEILER |