426 1/2 E 119TH ST 90061
Certificate Information: 426 1/2 E 119TH ST 90061
- Application / Permit
- 23014-10000-05269
- Plan Check / Job No.
- B23LA24148
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 18' DETACHED GARAGE AND (N) 21'6" X 30' IRREGULARLY SHAPED ADDITION (551 SF) TO CREATE (N) ACCESSORY DWELLING UNIT (875 SF) PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER WFPP
- Permit Issued
- Issued on 12/18/2024
- Issuing Office
- Current Status
- Issued on 12/18/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2023 | MADISON ODELL |
| Corrections Issued | 12/31/2023 | MADISON ODELL |
| Applicant returned to address corrections | 12/10/2024 | OMAR GARNICA |
| Plan Check Approved | 12/17/2024 | OMAR GARNICA |
| Issued | 12/18/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2024 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 3/12/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 5/10/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 11/11/2024 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/6/2024 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/3/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 4/25/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/16/2025 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 5/16/2025 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 5/20/2025 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 5/28/2025 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 8/14/2025 | Not Ready for Inspection | ANTHONY EGSON |
| MERV13>=Rough | 8/14/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 8/14/2025 | Corrections Issued | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 8/21/2025 | Conditional Approval | ANTHONY EGSON |
| Wood Frame | 8/26/2025 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/4/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 9/4/2025 | Not Ready for Inspection | ANTHONY EGSON |
| MERV13>=Rough | 9/4/2025 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/30/2025 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 10/30/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 11/18/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 11/18/2025 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/4/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/4/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 12/4/2025 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 12/4/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 12/4/2025 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/11/2025 | Partial Approval | ARTHUR NEGRETE |
| PLUMBING-Rough | 12/11/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 12/26/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 12/26/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 12/26/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 12/26/2025 | Partial Approval | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 12/26/2025 | Approved | ARTHUR NEGRETE |
| MERV13>=Rough | 12/26/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 12/26/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 1/8/2026 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 2/5/2026 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 2/5/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 4/15/2026 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 4/28/2026 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 6/2/2026 | Approved | ARTHUR NEGRETE |
| Final | 6/2/2026 | Corrections Issued | ARTHUR NEGRETE |
| Green Building Final | 6/2/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 6/2/2026 | Approved | ARTHUR NEGRETE |
| MERV13>=Final | 6/2/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 6/2/2026 | Corrections Issued | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 6/2/2026 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 6/2/2026 | Approved | ARTHUR NEGRETE |