2312 W 39TH ST 90008

Certificate Information: 2312 W 39TH ST 90008

Application / Permit
23014-10000-05223
Plan Check / Job No.
B23LA24020
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELING UNIT PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33(c)-(d), (g)
Permit Issued
Issued on 10/23/2024
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 DANIEL YIP
Corrections Issued 1/18/2024 DANIEL YIP
Quality Review Completed 1/22/2024 GARO TELMI
Applicant returned to address corrections 4/25/2024 DANIEL YIP
Applicant returned to address corrections 6/6/2024 DANIEL YIP
Plan Check Approved 10/23/2024 DANIEL YIP
Issued 10/23/2024 APPLICANT
CofO in Progress 10/6/2025 LUIS CASTRO
Permit Finaled 10/7/2025 DEROLD HAUFF
Permit Finaled 10/7/2025 DEROLD HAUFF
CofO Issued 10/7/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/1/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 2/5/2024 JEANIE LAM
Sewer availability Cleared 2/5/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/7/2024 JEANIE LAM

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: NA24587       ,
Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/14/2024 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Partial Approval BRENDAN MORELLI
Sewer 1/17/2025 Approved LUIS CASTRO
Underground Mechanical 1/17/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 2/14/2025 Approved LUIS CASTRO
HVAC-Rough 2/14/2025 Approved LUIS CASTRO
PLUMBING-Rough 2/14/2025 Approved LUIS CASTRO
Underground Mechanical 2/14/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Corrections Issued LUIS CASTRO
HVAC-Rough 2/28/2025 Approved LUIS CASTRO
Insulation 2/28/2025 Not Ready for Inspection LUIS CASTRO
BUILDING-Rough-Frame 3/7/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Approved LUIS CASTRO
Green Building Rough 3/7/2025 Partial Approval LUIS CASTRO
Interior/Exterior Lathing 3/7/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 3/11/2025 Approved LUIS CASTRO
Green Building Rough 3/11/2025 Approved LUIS CASTRO
Insulation 3/11/2025 Approved LUIS CASTRO
Drywall Nailing 3/27/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 3/27/2025 Approved LUIS CASTRO
Shower Pan 3/27/2025 Approved LUIS CASTRO
Final 8/15/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Final 8/15/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 8/15/2025 Not Ready for Inspection LUIS CASTRO
Final 8/21/2025 Corrections Issued MICHAEL LEWIS
Green Building Final 8/21/2025 Corrections Issued MICHAEL LEWIS
Smoke Detectors 8/21/2025 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 9/15/2025 Approved LUIS CASTRO
Final 9/15/2025 Corrections Issued LUIS CASTRO
Green Building Final 9/15/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Final 9/15/2025 Approved LUIS CASTRO
Smoke Detectors 9/15/2025 Approved LUIS CASTRO
Final 10/3/2025 OK to Issue CofO LUIS CASTRO
Green Building Final 10/3/2025 Approved LUIS CASTRO