17702 W BESSEMER ST 91316
Certificate Information: 17702 W BESSEMER ST 91316
- Application / Permit
- 23014-10000-05182
- Plan Check / Job No.
- B23LA23831
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 360 SF DET GARAGE + 393 SF ADDITION TO (N) 753 SF ADU PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 1/18/2024
- Issuing Office
- Current Status
- CofO Issued on 7/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/23/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 1/17/2024 | OMAR GARNICA |
| Issued | 1/18/2024 | APPLICANT |
| CofO in Progress | 6/10/2024 | MORRIS JACKSON |
| CofO in Progress | 6/11/2024 | MORRIS JACKSON |
| CofO in Progress | 6/12/2024 | MORRIS JACKSON |
| Permit Finaled | 7/10/2024 | JOHN JANSON |
| CofO Issued | 7/10/2024 | JOHN JANSON |
| Permit Finaled | 7/10/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/27/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/27/2023 | CARLOS AGUILERA |
| ZI | Cleared | 12/28/2023 | NATHAN ROMINE |
| Metro Rail approval | Cleared | 1/4/2024 | JENNIFER SU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/31/2024 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 2/15/2024 | Partial Approval | JEFFREY BULL |
| Pre-Inspection | 2/15/2024 | Approved | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 2/21/2024 | Corrections Issued | JON MCHUGH |
| Deputy Drilled-In Anchors | 2/23/2024 | Conditional Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 2/23/2024 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 3/14/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 3/14/2024 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 3/14/2024 | Not Ready for Inspection | JON MCHUGH |
| Deputy Wood Construction | 3/18/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 3/18/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 3/18/2024 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Approved | JON MCHUGH |
| HVAC-Rough | 3/18/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 3/18/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 3/18/2024 | Approved | JON MCHUGH |
| Wood Frame | 3/18/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 3/27/2024 | Partial Approval | GEVORK IPCHYAN |
| Insulation | 4/2/2024 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 4/2/2024 | Partial Approval | DAVID SCANTLIN |
| Sewer | 4/2/2024 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 4/2/2024 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 4/9/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 4/9/2024 | Approved | JON MCHUGH |
| Green Building Rough | 4/9/2024 | Approved | JON MCHUGH |
| Shower Pan | 4/9/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 4/11/2024 | Not Ready for Inspection | HENRY KIM |
| Interior/Exterior Lathing | 4/16/2024 | Approved | HENRY KIM |
| Final | 5/30/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 5/30/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 5/30/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 5/30/2024 | Approved | JON MCHUGH |
| Final | 6/7/2024 | Partial Approval | MORRIS JACKSON |
| Green Building Final | 6/7/2024 | Approved | MORRIS JACKSON |
| Final | 6/11/2024 | OK to Issue CofO | MORRIS JACKSON |
| Service/Power Release | 6/11/2024 | Approved | MORRIS JACKSON |