441 1/2 N MOUNTAIN VIEW AVE 90026
Certificate Information: 441 1/2 N MOUNTAIN VIEW AVE 90026
- Application / Permit
- 23014-10000-05178
- Plan Check / Job No.
- B23LA23797
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY BUILDING TO INCLUDE A 4-CAR CARPORT ON THE 1ST FLOOR AND NEW ADU ON THE 2ND FLOOR. (NO GPI REPORT)
- Permit Issued
- Issued on 11/25/2024
- Issuing Office
- Current Status
- CofO Issued on 4/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 1/19/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 1/24/2024 | KEN GILL |
| Building Plans Picked Up | 2/2/2024 | APPLICANT |
| Plan Check Approved | 11/20/2024 | MARCELA FRANQUEZ |
| Issued | 11/25/2024 | APPLICANT |
| Permit Finaled | 4/8/2026 | DEROLD HAUFF |
| CofO Issued | 4/8/2026 | DEROLD HAUFF |
| Permit Finaled | 4/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/15/2024 | VASIL MIHALEV |
| Low Impact Development (LID) | Cleared | 8/27/2024 | LUIS LUVANO |
| Address approval | Cleared | 8/28/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 8/28/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 8/29/2024 | DAVID LOPEZ |
| GPI Written Notices | Cleared | 11/20/2024 | MARCELA FRANQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mchantaf,, Kamal Beshara; Lic. No.: C51050 | 23315 SARATOGA SPRINGS PL MURRIETA, CA 92562 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/3/2025 | No Access for Inspection | FREDDIE RIVERA |
| Pre-Inspection | 2/5/2025 | Corrections Issued | FREDDIE RIVERA |
| Pre-Inspection | 2/21/2025 | Partial Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 2/26/2025 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 2/26/2025 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 3/4/2025 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/7/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Barrier | 3/7/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Subgrade | 3/7/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/28/2025 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 3/28/2025 | Corrections Issued | FREDDIE RIVERA |
| MERV13>=Rough | 3/28/2025 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 3/28/2025 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 3/28/2025 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Partial Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2025 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/27/2025 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 5/27/2025 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 5/27/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/30/2025 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 5/30/2025 | Partial Inspection | FREDDIE RIVERA |
| Special/Order Compliance | 5/30/2025 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/4/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Rough | 6/4/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| METHANE-Rough | 6/4/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/4/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/12/2025 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 6/12/2025 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 6/12/2025 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 6/12/2025 | Partial Approval | FREDDIE RIVERA |
| MERV13>=Rough | 6/12/2025 | Conditional Approval | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 6/12/2025 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 6/23/2025 | Approved | FREDDIE RIVERA |
| Insulation | 6/23/2025 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 7/25/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 7/25/2025 | Approved | REGINA MENDEZ |
| Structural Steel Frame | 9/17/2025 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 11/4/2025 | Partial Inspection | FREDDIE RIVERA |
| Underground Mechanical | 11/4/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 12/1/2025 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 12/1/2025 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 12/1/2025 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Final | 12/26/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 12/26/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 12/26/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/13/2026 | Approved | FREDDIE RIVERA |
| Final | 3/13/2026 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 3/13/2026 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 3/13/2026 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 3/13/2026 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 3/13/2026 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 3/13/2026 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 3/13/2026 | Approved | FREDDIE RIVERA |
| Final | 3/23/2026 | Corrections Issued | FREDDIE RIVERA |
| Service/Power Release | 3/23/2026 | Approved | FREDDIE RIVERA |
| Final | 4/1/2026 | Corrections Issued | FREDDIE RIVERA |
| Final | 4/6/2026 | Conditional Approval | FREDDIE RIVERA |