441 1/2 N MOUNTAIN VIEW AVE 90026

Certificate Information: 441 1/2 N MOUNTAIN VIEW AVE 90026

Application / Permit
23014-10000-05178
Plan Check / Job No.
B23LA23797
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY BUILDING TO INCLUDE A 4-CAR CARPORT ON THE 1ST FLOOR AND NEW ADU ON THE 2ND FLOOR. (NO GPI REPORT)
Permit Issued
Issued on 11/25/2024
Issuing Office
Current Status
CofO Issued on 4/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 MARCELA FRANQUEZ
Corrections Issued 1/19/2024 MARCELA FRANQUEZ
Quality Review Completed 1/24/2024 KEN GILL
Building Plans Picked Up 2/2/2024 APPLICANT
Plan Check Approved 11/20/2024 MARCELA FRANQUEZ
Issued 11/25/2024 APPLICANT
Permit Finaled 4/8/2026 DEROLD HAUFF
CofO Issued 4/8/2026 DEROLD HAUFF
Permit Finaled 4/8/2026 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/15/2024 VASIL MIHALEV
Low Impact Development (LID) Cleared 8/27/2024 LUIS LUVANO
Address approval Cleared 8/28/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 8/28/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 8/29/2024 DAVID LOPEZ
Sewer availability Cleared 8/29/2024 DAVID LOPEZ
GPI Written Notices Cleared 11/20/2024 MARCELA FRANQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mchantaf,, Kamal Beshara; Lic. No.: C51050 23315 SARATOGA SPRINGS PL      MURRIETA, CA 92562

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/3/2025 No Access for Inspection FREDDIE RIVERA
Pre-Inspection 2/5/2025 Corrections Issued FREDDIE RIVERA
Pre-Inspection 2/21/2025 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 2/26/2025 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 2/26/2025 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 3/4/2025 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 3/7/2025 Approved ALIZAH MAYAGOITIA
METHANE-Barrier 3/7/2025 Approved ALIZAH MAYAGOITIA
METHANE-Subgrade 3/7/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/28/2025 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/28/2025 Partial Approval FREDDIE RIVERA
Green Building Rough 3/28/2025 Corrections Issued FREDDIE RIVERA
MERV13>=Rough 3/28/2025 Partial Inspection FREDDIE RIVERA
METHANE-Rough 3/28/2025 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 3/28/2025 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Partial Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 5/27/2025 Partial Inspection FREDDIE RIVERA
HVAC-Rough 5/27/2025 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 5/27/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 5/30/2025 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 5/30/2025 Partial Inspection FREDDIE RIVERA
Special/Order Compliance 5/30/2025 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 6/4/2025 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Rough 6/4/2025 Not Ready for Inspection HAMIK HARTOUNIAN
METHANE-Rough 6/4/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 6/4/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/12/2025 Corrections Issued FREDDIE RIVERA
Green Building Rough 6/12/2025 Approved FREDDIE RIVERA
HVAC-Rough 6/12/2025 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 6/12/2025 Partial Approval FREDDIE RIVERA
MERV13>=Rough 6/12/2025 Conditional Approval FREDDIE RIVERA
Verify Sprinkler Sign Off 6/12/2025 Partial Inspection FREDDIE RIVERA
HVAC-Rough 6/23/2025 Approved FREDDIE RIVERA
Insulation 6/23/2025 Approved FREDDIE RIVERA
Drywall Nailing 7/25/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 7/25/2025 Approved REGINA MENDEZ
Structural Steel Frame 9/17/2025 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 11/4/2025 Partial Inspection FREDDIE RIVERA
Underground Mechanical 11/4/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 12/1/2025 Corrections Issued FREDDIE RIVERA
HVAC-Final 12/1/2025 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 12/1/2025 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Final 12/26/2025 Approved FREDDIE RIVERA
HVAC-Final 12/26/2025 Approved FREDDIE RIVERA
PLUMBING-Final 12/26/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 3/13/2026 Approved FREDDIE RIVERA
Final 3/13/2026 Corrections Issued FREDDIE RIVERA
Green Building Final 3/13/2026 Approved FREDDIE RIVERA
MERV13>=Final 3/13/2026 Approved FREDDIE RIVERA
MERV13>=Rough 3/13/2026 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Approved FREDDIE RIVERA
Service/Power Release 3/13/2026 Partial Inspection FREDDIE RIVERA
Smoke Detectors 3/13/2026 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 3/13/2026 Approved FREDDIE RIVERA
Final 3/23/2026 Corrections Issued FREDDIE RIVERA
Service/Power Release 3/23/2026 Approved FREDDIE RIVERA
Final 4/1/2026 Corrections Issued FREDDIE RIVERA
Final 4/6/2026 Conditional Approval FREDDIE RIVERA