5171 N CASPAR AVE 90041
Certificate Information: 5171 N CASPAR AVE 90041
- Application / Permit
- 23014-10000-05172
- Plan Check / Job No.
- B23LA23765
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: ADDITION AND REMODEL TO (E) SFD PER ENGINEER
- Permit Issued
- Issued on 3/20/2024
- Issuing Office
- Current Status
- CofO Issued on 7/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2023 | KHUONG TRUONG |
| Corrections Issued | 12/25/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 2/20/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 3/15/2024 | NEHEMIAS RAMOS |
| Issued | 3/20/2024 | APPLICANT |
| CofO in Progress | 7/25/2025 | DAVID WILLIAMS |
| Permit Finaled | 7/27/2025 | DEROLD HAUFF |
| CofO Issued | 7/27/2025 | DEROLD HAUFF |
| Permit Finaled | 7/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/29/2023 | ALEXANDER HELFER |
| Roof/Waste drainage to street | Cleared | 2/8/2024 | JEANIE LAM |
| Sewer availability | Cleared | 2/8/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2024 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/30/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 5/2/2024 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/2/2024 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/13/2024 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/13/2024 | Partial Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 5/14/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/15/2024 | Partial Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 5/15/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 6/21/2024 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 7/8/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/8/2024 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/16/2024 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 7/16/2024 | Approved | SCOTT FINNILA |
| HVAC-Rough | 7/16/2024 | Approved | SCOTT FINNILA |
| Insulation | 7/31/2024 | Conditional Approval | ANTHONY RAMOS |
| Shower Pan | 7/31/2024 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 8/2/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 8/2/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 8/13/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/28/2024 | Approved | CRAIG VAUGHAN |
| Final | 6/17/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 6/17/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 6/17/2025 | Approved | DAVID WILLIAMS |
| Final | 7/7/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Final | 7/25/2025 | OK to Issue CofO | DAVID WILLIAMS |