2319 1/2 N TEVIOT ST 90039

Certificate Information: 2319 1/2 N TEVIOT ST 90039

Application / Permit
23014-10000-05164
Plan Check / Job No.
B23LA23731
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Conversion of existing detached garage into ADU with addition per CA Govt. Code 65852.2(e)(1)(B)
Permit Issued
Issued on 2/19/2025
Issuing Office
Current Status
Issued on 2/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/17/2023 APPLICANT
Assigned to Plan Check Engineer 12/19/2023 JOSEPH RAFOLS
Corrections Issued 12/20/2023 JOSEPH RAFOLS
Applicant returned to address corrections 2/4/2025 SHANGQIN XIE
Applicant returned to address corrections 2/6/2025 ZAW HAN
Plan Check Approved 2/12/2025 ZAW HAN
Issued 2/19/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/8/2024 ARNULFO CHAMU
Roof/Waste drainage to street Cleared 1/8/2024 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 1/9/2024 ARNULFO CHAMU
Sewer availability Cleared 1/9/2024 ARNULFO CHAMU
Miscellaneous Cleared 1/17/2025 ALBERT TAM
Grading Pre-Inspection Cleared 2/7/2025 MICHAEL TEMPLE

Contact Information

Contractor Oakasa Construction Services; Lic. No.: 1098151-B       ,
Contractor Oakasa Inc; Lic. No.: 1098151-B       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606
Engineer Grigoryan,, Souren; Lic. No.: NA93320       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/18/2025 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 7/7/2025 Partial Approval BRENDAN MORELLI
Underground Mechanical 7/7/2025 Partial Approval BRENDAN MORELLI
Deputy Drilled-In Anchors 7/17/2025 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/18/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/25/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/25/2025 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 8/25/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/29/2025 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/29/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 8/29/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 8/29/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/4/2025 Approved HAMIK HARTOUNIAN
Special/Order Compliance 9/4/2025 Partial Inspection OSVALDO PARAMO
Insulation 9/8/2025 Corrections Issued JEFFREY MEAD
Interior/Exterior Lathing 9/8/2025 Partial Approval JEFFREY MEAD
Shower Pan 9/8/2025 Approved JEFFREY MEAD
Interior/Exterior Lathing 9/10/2025 Partial Approval ALEX COLIN
Insulation 9/11/2025 Corrections Issued HAMIK HARTOUNIAN
Drywall Nailing 9/17/2025 Not Ready for Inspection ALEX COLIN
Interior/Exterior Lathing 9/17/2025 Approved ALEX COLIN
Interior/Exterior Lathing 9/19/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 5/26/2026 Approved HAMIK HARTOUNIAN
Final 5/26/2026 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 5/26/2026 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 5/26/2026 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Final 5/26/2026 Partial Approval HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 5/26/2026 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 5/28/2026 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 5/28/2026 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 5/28/2026 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 6/1/2026 Corrections Issued WILLIAM SIERRA
Final 6/1/2026 Corrections Issued WILLIAM SIERRA
Green Building Final 6/1/2026 Not Ready for Inspection WILLIAM SIERRA
HVAC-Final 6/1/2026 Corrections Issued WILLIAM SIERRA
PLUMBING-Final 6/1/2026 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 6/1/2026 SGSOV Not Required WILLIAM SIERRA
Special/Order Compliance 6/1/2026 Not Ready for Inspection ALIZAH MAYAGOITIA