1653 W 84TH PL 90047
Certificate Information: 1653 W 84TH PL 90047
- Application / Permit
- 23014-10000-05162
- Plan Check / Job No.
- B23LA23728
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN NEW ADDITION TO THE REAR OF THE (E) SFD AND CONVERT (E) STORAGE ROOM TO (N) POWDER ROOM *** "COMPLY WITH DEPARTMENT ORDER effective date 09/20/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 967150.***
- Permit Issued
- Issued on 3/19/2024
- Issuing Office
- Current Status
- CofO Issued on 1/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2024 | JOHNPAUL ISIP |
| Corrections Issued | 1/23/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 3/14/2024 | DAVID CASTILLO |
| Issued | 3/19/2024 | APPLICANT |
| CofO in Progress | 1/14/2025 | SABAS ALONSO |
| CofO Issued | 1/15/2025 | DEROLD HAUFF |
| Permit Finaled | 1/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/26/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 1/29/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vega,, Cayetano Gonzalez; Lic. No.: NA43117 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/16/2024 | Corrections Issued | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 4/19/2024 | Approved | JOSE MACIAS |
| Insulation | 4/26/2024 | Partial Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 5/13/2024 | Conditional Approval | JOSE MACIAS |
| Green Building Rough | 5/13/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Rough | 5/13/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 5/13/2024 | Approved | JOSE MACIAS |
| Insulation | 5/20/2024 | No Access for Inspection | JOSE MACIAS |
| Interior/Exterior Lathing | 5/20/2024 | No Access for Inspection | JOSE MACIAS |
| Shower Pan | 5/20/2024 | No Access for Inspection | JOSE MACIAS |
| Insulation | 5/22/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 5/22/2024 | Approved | JOSE MACIAS |
| Shower Pan | 5/22/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 5/24/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 5/24/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 7/3/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 7/3/2024 | Approved | JOSE MACIAS |
| Final | 7/3/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 7/3/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 7/3/2024 | Approved | JOSE MACIAS |
| Final | 1/6/2025 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 1/6/2025 | Approved | JOSE MACIAS |
| Final | 1/13/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 1/13/2025 | Approved | SABAS ALONSO |