7901 S BELAND AVE 90045
Certificate Information: 7901 S BELAND AVE 90045
- Application / Permit
- 23014-10000-05161
- Plan Check / Job No.
- B23LA22199
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- ePlan. Ground floor addition to existing deatched garage for new recreation room.
- Permit Issued
- Issued on 4/12/2024
- Issuing Office
- Current Status
- Issued on 4/12/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 12/15/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 12/15/2023 | GARO TELMI |
| Plan Check Approved | 4/10/2024 | TU HUA |
| Issued | 4/12/2024 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 3/4/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 3/4/2024 | DARIN LAM |
| Sewer availability | Cleared | 3/4/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2024 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 4/10/2024 | MAHNAZ NOURHASHEMI |
Contact Information
| Architect | Belak-Berger,, Charles Peter; Lic. No.: NA13657 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/1/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Deputy Reinf. Concrete | 5/24/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Pre-Inspection | 6/25/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 6/27/2024 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 6/27/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 6/27/2024 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 11/13/2024 | Approved | MICHAEL ALLEN |
| Gas Test | 11/13/2024 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 11/13/2024 | Approved | MICHAEL ALLEN |
| Wood Frame | 11/15/2024 | Corrections Issued | MICHAEL ALLEN |
| Wood Frame | 12/13/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| Insulation | 1/31/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 5/8/2025 | Partial Approval | RUBEN RIVAS |
| PLUMBING-Rough | 6/26/2025 | Corrections Issued | RUBEN RIVAS |
| Gas Test | 9/23/2025 | Corrections Issued | RUBEN RIVAS |
| HVAC-Rough | 9/23/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Rough | 9/23/2025 | Partial Approval | RUBEN RIVAS |
| HVAC-Final | 10/27/2025 | Partial Approval | RUBEN RIVAS |
| Gas Test | 11/6/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 11/6/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Final | 11/7/2025 | Approved | RUBEN RIVAS |
| Service/Power Release | 11/17/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 12/3/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/8/2025 | Approved | ANTHONY EGSON |
| HVAC-Final | 12/8/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 12/8/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/17/2025 | Approved | ANTHONY EGSON |
| Final | 12/17/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 12/17/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/17/2025 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/17/2025 | SGSOV Not Required | ANTHONY EGSON |
| Smoke Detectors | 12/17/2025 | Approved | ANTHONY EGSON |