1150 1/2 S DOHENY DR 90035

Certificate Information: 1150 1/2 S DOHENY DR 90035

Application / Permit
23014-10000-05148
Plan Check / Job No.
B23LA23652
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED 2-CAR GARAGE INTO NEW ADU WITH 1-STORY ADDITION (12'-6" X 11') per CA Govt. Code 65852.2(e)(1)(D) and applicable part 2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 7/8/2024
Issuing Office
Metro
Current Status
Issued on 7/8/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/14/2023 APPLICANT
Assigned to Plan Check Engineer 12/20/2023 LUKE GONZALES
Corrections Issued 12/23/2023 LUKE GONZALES
Building Plans Picked Up 12/29/2023 APPLICANT
Plan Check Approved 7/8/2024 JOSEPH RAFOLS
Issued 7/8/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/16/2024 DARIN LAM
Tenant Habitability Plan Cleared 1/17/2024 RICARDO BOHORQUEZ
Construction near power lines Cleared 5/8/2024 RIDWAN HARDY
Roof/Waste drainage to street Cleared 6/24/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 6/27/2024 DARIN LAM
Sewer availability Cleared 6/27/2024 DARIN LAM
Hold Cleared 10/1/2024 ALEXIS SCHULTZ

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/2/2024 Not Ready for Inspection FARHAD DADBIN
METHANE-Barrier 10/2/2024 Not Ready for Inspection FARHAD DADBIN
METHANE-Subgrade 10/2/2024 Not Ready for Inspection FARHAD DADBIN
Footing/Foundation/Slab 10/8/2024 Not Ready for Inspection AMANUEL BERHE
METHANE-Barrier 10/8/2024 Approved AMANUEL BERHE
METHANE-Subgrade 10/8/2024 Approved AMANUEL BERHE
Footing/Foundation/Slab 10/9/2024 Not Ready for Inspection FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 5/20/2025 Corrections Issued FARHAD DADBIN
Footing/Foundation/Slab 8/14/2025 Not Ready for Inspection FARHAD DADBIN
Footing/Foundation/Slab 8/20/2025 Approved FARHAD DADBIN
Pre-Inspection 10/23/2025 Partial Approval FARHAD DADBIN
Green Building Rough 1/14/2026 Approved FARHAD DADBIN
METHANE-Rough 1/14/2026 Approved FARHAD DADBIN
Wood Frame 1/14/2026 Partial Approval FARHAD DADBIN
Wood Frame 2/3/2026 Approved FARHAD DADBIN
Interior/Exterior Lathing 3/3/2026 Partial Approval FARHAD DADBIN
Drywall Nailing 3/16/2026 Approved FARHAD DADBIN
Interior/Exterior Lathing 3/16/2026 Approved FARHAD DADBIN