3775 1/2 S BOISE AVE 90066
Certificate Information: 3775 1/2 S BOISE AVE 90066
- Application / Permit
- 23014-10000-05139
- Plan Check / Job No.
- B23LA23621
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 26'-2" X 14'-9" ADDITION AND CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER ENGINEER
- Permit Issued
- Issued on 3/20/2024
- Issuing Office
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 12/19/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 2/15/2024 | DANIEL ABRAMYAN |
| Issued | 3/20/2024 | APPLICANT |
| CofO in Progress | 10/15/2024 | JESUS PINEDA |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
| CofO Issued | 10/15/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2024 | DARIN LAM |
| Sewer availability | Cleared | 1/11/2024 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 1/17/2024 | VASIL MIHALEV |
| Roof/Waste drainage to street | Cleared | 1/29/2024 | DARIN LAM |
| Specific Plan | Cleared | 2/7/2024 | PEDRO AYALA |
Contact Information
| Architect | Perella,, Ryan Adam; Lic. No.: NA30833 | , |
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | , |
| Engineer | Sayah,, Daniel H; Lic. No.: NA67905 | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/30/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/30/2024 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/7/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/12/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/9/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 7/9/2024 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 7/11/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/12/2024 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 7/23/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 7/23/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 8/5/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/5/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/19/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 10/9/2024 | Corrections Issued | JESUS PINEDA |
| Final | 10/9/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 10/9/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 10/9/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/9/2024 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 10/9/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 10/10/2024 | Approved | JESUS PINEDA |
| Final | 10/10/2024 | OK to Issue CofO | JESUS PINEDA |
| HVAC-Final | 10/10/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 10/10/2024 | Approved | JESUS PINEDA |