1008 E M ST 90744
Certificate Information: 1008 E M ST 90744
- Application / Permit
- 23014-10000-05121
- Plan Check / Job No.
- B23LA23564
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 100 SF ADDITION TO (E) SFD AT FRONT OF LOT ALL WORK PER WFPP 2 OF 2
- Permit Issued
- Issued on 6/18/2024
- Issuing Office
- Metro
- Current Status
- Issued on 6/18/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2023 | SAMUEL GONZALEZ |
| Corrections Issued | 12/16/2023 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 12/22/2023 | APPLICANT |
| Applicant returned to address corrections | 1/16/2024 | WEIJIAN HUANG |
| Plan Check Approved | 6/18/2024 | JOSEPH RAFOLS |
| Issued | 6/18/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2024 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/13/2024 | KHAING AYE |
Contact Information
| Contractor | Castro O Construction; Lic. No.: 1036305-B | 2269 SANTA ANA N LOS ANGELES, CA 90059 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/26/2024 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/3/2024 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 7/3/2024 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 7/3/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Partial Approval | EUGENE CASSIDY |
| Gas Test | 7/31/2024 | Approved | EUGENE CASSIDY |
| Insulation | 7/31/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 7/31/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2024 | Partial Approval | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 9/9/2024 | Conditional Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Partial Approval | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 10/4/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/16/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/16/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 10/16/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 10/16/2024 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 10/16/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/16/2024 | Approved | EUGENE CASSIDY |
| Wood Frame | 10/16/2024 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/23/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/23/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 10/23/2024 | Approved | EUGENE CASSIDY |
| Insulation | 10/23/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/23/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 11/6/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 2/6/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 2/6/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 2/6/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 2/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/23/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 5/23/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 5/23/2025 | No Access for Inspection | EUGENE CASSIDY |
| Final | 5/28/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 5/28/2025 | Corrections Issued | EUGENE CASSIDY |
| Final | 10/29/2025 | Corrections Issued | EUGENE CASSIDY |
| Smoke Detectors | 10/29/2025 | Not Ready for Inspection | EUGENE CASSIDY |