1315 W STORM PKWY 90501
Certificate Information: 1315 W STORM PKWY 90501
- Application / Permit
- 23014-10000-05116
- Plan Check / Job No.
- B23LA23559
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- EPLAN PROPOSED MAJOR REMODEL TO EXISTING WAREHOUSE/OFFICE BUILDING. SCOPE INCLUDE DEMOLITION OF EXISTING MEZZANINE LEVEL, REMODEL/RECONFIGURE EXISTING OFFICE AREA.
- Permit Issued
- Issued on 6/28/2024
- Issuing Office
- Current Status
- CofO Issued on 4/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2023 | MICHAEL LOPEZ |
| Assigned to Zoning Architect | 12/14/2023 | MICHAEL LOPEZ |
| Corrections Issued | 12/27/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 12/27/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/6/2024 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/10/2024 | MICHAEL LOPEZ |
| Plan Check Approved | 6/28/2024 | MICHAEL LOPEZ |
| Issued | 6/28/2024 | APPLICANT |
| Permit Finaled | 4/14/2025 | JOEY BUCHANAN |
| CofO Issued | 4/14/2025 | JOEY BUCHANAN |
| Permit Finaled | 4/14/2025 | JOEY BUCHANAN |
Permit Application Clearance Information
| Highway dedication | Cleared | 1/4/2024 | KHAING AYE |
| Miscellaneous | Cleared | 4/11/2024 | GEORGIA SMITH |
| Green Code | Cleared | 4/16/2024 | Ricardo Ramirez Solis |
| DAS Clearance | Cleared | 5/9/2024 | Ricardo Ramirez Solis |
| Zoning Plan Check | Cleared | 6/28/2024 | Ricardo Ramirez Solis |
Contact Information
| Architect | Dwyer,, Mark Steven; Lic. No.: NA23283 | , |
| Contractor | Norm Wilson & Sons Inc; Lic. No.: 435700-B | , |
| Engineer | Rosepink,, Dustin; Lic. No.: S5885 | 24255 VIA MADRUGADA MISSION VIEJO, CA 92692 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 7/11/2024 | Not Ready for Inspection | AMANUEL BERHE |
| Pre-Inspection | 7/11/2024 | Approved | AMANUEL BERHE |
| Footing/Foundation/Slab | 7/12/2024 | Partial Inspection | AMANUEL BERHE |
| Final | 7/15/2024 | Not Ready for Inspection | AMANUEL BERHE |
| Green Building Final | 7/15/2024 | Not Ready for Inspection | AMANUEL BERHE |
| Green Building Rough | 7/15/2024 | Not Ready for Inspection | AMANUEL BERHE |
| METHANE-Final | 7/15/2024 | Not Ready for Inspection | AMANUEL BERHE |
| METHANE-Rough | 7/15/2024 | Not Ready for Inspection | AMANUEL BERHE |
| Reinforced Masonry Frame | 7/15/2024 | Not Ready for Inspection | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 7/15/2024 | SGSOV Not Ready | AMANUEL BERHE |
| Smoke Detectors | 7/15/2024 | Approved | AMANUEL BERHE |
| Wood Frame | 7/15/2024 | Partial Inspection | AMANUEL BERHE |
| Footing/Foundation/Slab | 7/24/2024 | Approved | AMANUEL BERHE |
| Deputy Drilled-In Anchors | 7/25/2024 | Approved | AMANUEL BERHE |
| Excavation/Setback/Form/Re-Bar | 7/29/2024 | Approved | AMANUEL BERHE |
| Light Gage Steel Frame | 7/31/2024 | Partial Inspection | AMANUEL BERHE |
| Footing/Foundation/Slab | 8/8/2024 | Not Ready for Inspection | AMANUEL BERHE |
| Footing/Foundation/Slab | 8/9/2024 | Not Ready for Inspection | AMANUEL BERHE |
| Footing/Foundation/Slab | 8/12/2024 | Partial Inspection | AMANUEL BERHE |
| Light Gage Steel Frame | 8/16/2024 | Partial Inspection | AMANUEL BERHE |
| Light Gage Steel Frame | 8/21/2024 | Partial Inspection | AMANUEL BERHE |
| Drywall Nailing | 8/26/2024 | Partial Inspection | AMANUEL BERHE |
| Insulation | 8/26/2024 | Partial Inspection | AMANUEL BERHE |
| Insulation | 8/28/2024 | Approved | AMANUEL BERHE |
| Light Gage Steel Frame | 9/3/2024 | Approved | AMANUEL BERHE |
| Deputy Drilled-In Anchors | 9/6/2024 | Conditional Approval | AMANUEL BERHE |
| Deputy Steel/Welding | 9/6/2024 | Conditional Approval | AMANUEL BERHE |
| Drywall Nailing | 9/10/2024 | Partial Inspection | AMANUEL BERHE |
| Deputy Reinf. Concrete | 9/17/2024 | Conditional Approval | AMANUEL BERHE |
| T-Bar Ceiling | 9/24/2024 | Not Ready for Inspection | AMANUEL BERHE |
| Deputy Reinf. Concrete | 9/27/2024 | Conditional Approval | AMANUEL BERHE |
| Excavation/Setback/Form/Re-Bar | 10/1/2024 | Partial Approval | JOEY BUCHANAN |
| Deputy Steel/Welding | 10/7/2024 | Conditional Approval | AMANUEL BERHE |
| T-Bar Ceiling | 10/17/2024 | Approved | AMANUEL BERHE |
| T-Bar Ceiling | 10/22/2024 | Approved | AMANUEL BERHE |
| Final | 12/12/2024 | Conditional Approval | MICHAEL PETRUSKO |
| Green Building Final | 12/12/2024 | Approved | MICHAEL PETRUSKO |
| Green Building Rough | 12/12/2024 | Approved | MICHAEL PETRUSKO |
| METHANE-Final | 12/12/2024 | Approved | MICHAEL PETRUSKO |
| METHANE-Rough | 12/12/2024 | Approved | MICHAEL PETRUSKO |
| Reinforced Masonry Frame | 12/12/2024 | Approved | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 12/12/2024 | SGSOV Approved | MICHAEL PETRUSKO |
| Deputy Drilled-In Anchors | 12/17/2024 | Conditional Approval | MICHAEL PETRUSKO |