2330 S OVERLAND AVE 90064

Certificate Information: 2330 S OVERLAND AVE 90064

Application / Permit
23014-10000-05106
Plan Check / Job No.
B23LA23425
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Ground Floor Addition and Remodel to an (E) 1-Story SFD
Permit Issued
Issued on 3/5/2024
Issuing Office
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2023 APPLICANT
Assigned to Plan Check Engineer 12/15/2023 DAVID CASTILLO
Corrections Issued 12/15/2023 DAVID CASTILLO
Plan Check Approved 3/1/2024 DAVID CASTILLO
Issued 3/5/2024 APPLICANT
CofO in Progress 12/13/2024 STEPHANIE SWANSON
Permit Finaled 12/17/2024 RICHARD STEINBACH
CofO Issued 12/17/2024 RICHARD STEINBACH
Permit Finaled 12/17/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/21/2023 MICHAEL TEMPLE
Roof/Waste drainage to street Cleared 1/18/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 1/18/2024 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 1/24/2024 KIMBERLY HERNANDEZ

Contact Information

Architect Woodcraft,, Astra E; Lic. No.: NA32722       ,
Contractor Owner-Builder       ,
Engineer Yamini,, Soly; Lic. No.: NA33719       ,

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/24/2024 Partial Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 5/9/2024 Approved SEAN HAUPT
Footing/Foundation/Slab 5/9/2024 Approved SEAN HAUPT
METHANE-Barrier 5/9/2024 Approved SEAN HAUPT
METHANE-Subgrade 5/9/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 6/4/2024 Partial Approval STEPHANIE SWANSON
Deputy Wood Construction 6/18/2024 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 6/24/2024 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/24/2024 Corrections Issued STEPHANIE SWANSON
Green Building Rough 6/24/2024 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Approved CARLOS MATAMOROS
Green Building Rough 7/3/2024 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 7/15/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 7/15/2024 Conditional Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 7/23/2024 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 7/23/2024 Approved STEPHANIE SWANSON
Green Building Rough 7/23/2024 Approved STEPHANIE SWANSON
HVAC-Rough 7/23/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 8/1/2024 Corrections Issued STEPHANIE SWANSON
Insulation 8/1/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 8/7/2024 Approved STEPHANIE SWANSON
Drywall Nailing 8/7/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 8/7/2024 Partial Approval STEPHANIE SWANSON
Shower Pan 8/7/2024 Approved STEPHANIE SWANSON
Special/Order Compliance 8/7/2024 Partial Inspection REGINA MENDEZ
Interior/Exterior Lathing 8/9/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Final 11/15/2024 Corrections Issued STEPHANIE SWANSON
Final 11/15/2024 Corrections Issued STEPHANIE SWANSON
Green Building Final 11/15/2024 Approved STEPHANIE SWANSON
HVAC-Final 11/15/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 11/15/2024 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 11/15/2024 SGSOV Not Ready STEPHANIE SWANSON
Smoke Detectors 11/15/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Final 11/20/2024 Approved STEPHANIE SWANSON
Final 11/20/2024 Partial Approval STEPHANIE SWANSON
HVAC-Final 11/20/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 11/20/2024 Partial Approval STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Approved STEPHANIE SWANSON
PLUMBING-Final 11/22/2024 Approved STEPHANIE SWANSON
Final 12/13/2024 OK to Issue CofO STEPHANIE SWANSON