4902 E BUCHANAN ST 90042

Certificate Information: 4902 E BUCHANAN ST 90042

Application / Permit
23014-10000-05099
Plan Check / Job No.
B23LA23407
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E)Building. AND VOLUNTARY ACCESSIBILITY UPGRADES
Permit Issued
Issued on 6/6/2024
Issuing Office
Metro
Current Status
Permit Finaled on 10/23/2024

Permit Application Status History

Submitted 12/12/2023 APPLICANT
Assigned to Plan Check Engineer 1/4/2024 GEORGE JOLAKIAN
Corrections Issued 2/1/2024 GEORGE JOLAKIAN
Quality Review Completed 2/2/2024 KEN GILL
Building Plans Picked Up 2/16/2024 APPLICANT
Plan Check Approved 4/16/2024 GEORGE JOLAKIAN
Issued 6/6/2024 APPLICANT
Permit Finaled 10/22/2024 ALIZAH MAYAGOITIA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/1/2024 SERGIO VALENZUELA

Contact Information

Contractor R & E Development Partners Llc; Lic. No.: 1115897-B P O BOX 2064      VICTORVILLE, CA 92395
Engineer Astourian,, Sevag Gary; Lic. No.: S5245 2575 LAMBERT DR      PASADENA, CA 91107

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/19/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 7/19/2024 Corrections Issued LILIANA PORTILLO
Pre-Inspection 7/19/2024 Partial Inspection LILIANA PORTILLO
PLUMBING-Rough 7/24/2024 Approved OSVALDO PARAMO
Deputy Drilled-In Anchors 7/30/2024 Conditional Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/1/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 8/2/2024 Approved ALIZAH MAYAGOITIA
Wood Frame 8/2/2024 Corrections Issued ALIZAH MAYAGOITIA
Wood Frame 8/6/2024 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 8/9/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/9/2024 Corrections Issued ALIZAH MAYAGOITIA
Reinforced Concrete Frame 8/9/2024 Corrections Issued ALIZAH MAYAGOITIA
Underground Mechanical 8/9/2024 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/14/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/14/2024 Partial Approval ALIZAH MAYAGOITIA
Deputy Reinf. Concrete 8/15/2024 Conditional Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 8/20/2024 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Rough 8/20/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 8/20/2024 Corrections Issued OSVALDO PARAMO
Wood Frame 8/20/2024 Corrections Issued ALIZAH MAYAGOITIA
Wood Frame 9/6/2024 Partial Approval ALIZAH MAYAGOITIA
Insulation 9/10/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/10/2024 Partial Approval ALIZAH MAYAGOITIA
Shower Pan 9/10/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 9/13/2024 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 10/9/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 10/22/2024 Approved ALIZAH MAYAGOITIA
Final 10/22/2024 Permit Finaled ALIZAH MAYAGOITIA
HVAC-Final 10/22/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 10/22/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 10/22/2024 Approved ALIZAH MAYAGOITIA