4902 E BUCHANAN ST 90042
Certificate Information: 4902 E BUCHANAN ST 90042
- Application / Permit
- 23014-10000-05099
- Plan Check / Job No.
- B23LA23407
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E)Building. AND VOLUNTARY ACCESSIBILITY UPGRADES
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 10/23/2024
Permit Application Status History
| Submitted | 12/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 2/1/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 2/2/2024 | KEN GILL |
| Building Plans Picked Up | 2/16/2024 | APPLICANT |
| Plan Check Approved | 4/16/2024 | GEORGE JOLAKIAN |
| Issued | 6/6/2024 | APPLICANT |
| Permit Finaled | 10/22/2024 | ALIZAH MAYAGOITIA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/1/2024 | SERGIO VALENZUELA |
Contact Information
| Contractor | R & E Development Partners Llc; Lic. No.: 1115897-B | P O BOX 2064 VICTORVILLE, CA 92395 |
| Engineer | Astourian,, Sevag Gary; Lic. No.: S5245 | 2575 LAMBERT DR PASADENA, CA 91107 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/19/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 7/19/2024 | Corrections Issued | LILIANA PORTILLO |
| Pre-Inspection | 7/19/2024 | Partial Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 7/24/2024 | Approved | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 7/30/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/1/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/2/2024 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 8/2/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Wood Frame | 8/6/2024 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 8/9/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/9/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Reinforced Concrete Frame | 8/9/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Underground Mechanical | 8/9/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/14/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/14/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Reinf. Concrete | 8/15/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/20/2024 | Corrections Issued | OSVALDO PARAMO |
| Wood Frame | 8/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Wood Frame | 9/6/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 9/10/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 9/10/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Shower Pan | 9/10/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 9/13/2024 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 10/9/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/22/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/22/2024 | Permit Finaled | ALIZAH MAYAGOITIA |
| HVAC-Final | 10/22/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 10/22/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 10/22/2024 | Approved | ALIZAH MAYAGOITIA |