2829 1/2 S WELLINGTON ROAD 90016
Certificate Information: 2829 1/2 S WELLINGTON ROAD 90016
- Application / Permit
- 23014-10000-05081
- Plan Check / Job No.
- B23LA23332
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH IRREGULAR SHAPED ADDITION TO (N) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 6/17/2024
- Issuing Office
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 12/16/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 5/22/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 6/1/2024 | ALEC MOUSAKHANIAN |
| No Progress | 6/13/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 6/13/2024 | ALEC MOUSAKHANIAN |
| Issued | 6/17/2024 | APPLICANT |
| CofO in Progress | 12/20/2024 | JUSTIN HAWLEY |
| Permit Finaled | 1/9/2025 | DEROLD HAUFF |
| CofO Issued | 1/9/2025 | DEROLD HAUFF |
| Permit Finaled | 1/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/17/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/17/2024 | RIDWAN HARDY |
| Address approval | Cleared | 5/23/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 5/23/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 5/30/2024 | DAVID LOPEZ |
Contact Information
| Contractor | J T Construction; Lic. No.: 871971-B | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/5/2024 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 7/11/2024 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 7/25/2024 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/3/2024 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 10/3/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 10/7/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 10/7/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/7/2024 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 10/17/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/17/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 10/31/2024 | Corrections Issued | RONNIE MINDANAO |
| Gas Test | 11/4/2024 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 11/4/2024 | Corrections Issued | JUSTIN HAWLEY |
| Gas Test | 11/7/2024 | Approved | BRENDAN MORELLI |
| Final | 12/12/2024 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 12/12/2024 | Approved | JUSTIN HAWLEY |
| Green Building Final | 12/12/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 12/12/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 12/12/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 12/20/2024 | Approved | JUSTIN HAWLEY |
| Final | 12/20/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| Green Building Final | 12/20/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 12/20/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 12/20/2024 | Approved | JUSTIN HAWLEY |