12209 W HAVELOCK AVE 90230
Certificate Information: 12209 W HAVELOCK AVE 90230
- Application / Permit
- 23014-10000-05076
- Plan Check / Job No.
- B23LA23319
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: EXTERIOR REMODEL, INTERIOR REMODEL, 1ST AND 2ND FLOOR ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 2/16/2024
- Issuing Office
- Current Status
- CofO Issued on 9/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2023 | DANIEL YIP |
| Corrections Issued | 12/17/2023 | DANIEL YIP |
| Quality Review Completed | 12/19/2023 | GARO TELMI |
| Plan Check Approved | 2/16/2024 | DANIEL YIP |
| Issued | 2/16/2024 | APPLICANT |
| CofO in Progress | 9/13/2024 | JESUS PINEDA |
| Permit Finaled | 9/16/2024 | RICHARD STEINBACH |
| CofO Issued | 9/16/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/16/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/2/2024 | ANDREA SAINT-ANTONIN |
| Roof/Waste drainage to street | Cleared | 2/12/2024 | ANDREA SAINT-ANTONIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2024 | ANDREA SAINT-ANTONIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/5/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/13/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/13/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 5/13/2024 | Partial Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/13/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Insulation | 5/20/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Shower Pan | 5/20/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 5/21/2024 | Partial Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/28/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 5/28/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/28/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 5/28/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/31/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 5/31/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/31/2024 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 5/31/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 6/6/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 6/17/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/28/2024 | Corrections Issued | JESUS PINEDA |
| Final | 8/28/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 8/28/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 8/28/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/28/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/28/2024 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 8/28/2024 | Approved | JESUS PINEDA |
| Smoke Detectors | 8/28/2024 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 8/28/2024 | Partial Inspection | HERBERT GIRON |
| Special/Order Compliance | 8/28/2024 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 8/30/2024 | Approved | JESUS PINEDA |
| Final | 8/30/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 8/30/2024 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 8/30/2024 | Approved | JESUS PINEDA |
| Final | 9/9/2024 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 9/9/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 9/9/2024 | Approved | JESUS PINEDA |