10724 S HICKORY ST 90059
Certificate Information: 10724 S HICKORY ST 90059
- Application / Permit
- 23014-10000-05072
- Plan Check / Job No.
- B23LA23303
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 27'-0" x 18'-1" IRREGULAR SHAPED ADDITION AND 5'-0" x 3'-6" PORCH ADDITION TO THE (E) 18'-1" x 20'-1" DETACHED GARAGE AND CONVERT IT INTO A NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 3/26/2024
- Issuing Office
- Current Status
- CofO Issued on 2/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2023 | SARKIS HARABEDIAN |
| Corrections Issued | 12/15/2023 | SARKIS HARABEDIAN |
| Plan Check Approved | 3/19/2024 | ISIS ARGUETA |
| Issued | 3/26/2024 | APPLICANT |
| CofO in Progress | 2/18/2025 | JOSEPH MCGARRY |
| Permit Finaled | 2/19/2025 | ANSON MAGLASANG |
| CofO Issued | 2/19/2025 | ANSON MAGLASANG |
| Permit Finaled | 2/19/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 2/20/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 3/7/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sandoval,, Martin; Lic. No.: NA56905 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/9/2024 | Partial Approval | BEN MOLSTAD |
| Deputy Drilled-In Anchors | 5/21/2024 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 5/29/2024 | Partial Approval | BEN MOLSTAD |
| PLUMBING-Rough | 5/29/2024 | Partial Approval | BEN MOLSTAD |
| PLUMBING-Rough | 5/31/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 7/24/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 7/24/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/10/2024 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 10/10/2024 | Not Ready for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Approved | BARRY HACHE |
| Green Building Rough | 10/10/2024 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 10/10/2024 | Not Ready for Inspection | BARRY HACHE |
| Underground Mechanical | 10/10/2024 | Approved | BARRY HACHE |
| Green Building Rough | 10/17/2024 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 10/17/2024 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 10/24/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/24/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 10/24/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/24/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/30/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/30/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 10/30/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/30/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/8/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/8/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 11/8/2024 | Approved | ANTHONY EGSON |
| Insulation | 11/18/2024 | Partial Approval | ANTHONY EGSON |
| Insulation | 11/26/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 12/6/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/27/2024 | Approved | ANTHONY EGSON |
| Shower Pan | 12/27/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/16/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 2/11/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 2/11/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 2/11/2025 | Approved | BEN MOLSTAD |
| Green Building Final | 2/11/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 2/11/2025 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 2/11/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 2/11/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 2/13/2025 | Approved | JOSEPH MCGARRY |
| Final | 2/13/2025 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Final | 2/13/2025 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 2/13/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/13/2025 | SGSOV Approved | JOSEPH MCGARRY |
| Final | 2/18/2025 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 2/18/2025 | Approved | JOSEPH MCGARRY |