2755 S GRANVILLE AVE 90064

Certificate Information: 2755 S GRANVILLE AVE 90064

Application / Permit
23014-10000-05064
Plan Check / Job No.
B23LA22600
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: ADDITION TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 2/16/2024
Issuing Office
Current Status
CofO Issued on 10/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 DANIEL YIP
Corrections Issued 12/9/2023 DANIEL YIP
Quality Review Completed 12/11/2023 PRANITA SHAH
Applicant returned to address corrections 2/13/2024 DANIEL YIP
Plan Check Approved 2/14/2024 DANIEL YIP
Issued 2/16/2024 APPLICANT
CofO in Progress 10/6/2025 KIRK SANDERS
Permit Finaled 10/21/2025 RICHARD STEINBACH
CofO Issued 10/21/2025 RICHARD STEINBACH
Permit Finaled 10/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/13/2023 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 12/19/2023 LIAM ODONOVAN
Specific Plan Cleared 1/29/2024 MOHAMMAD HASAN

Contact Information

Contractor Bela Remodeling; Lic. No.: 1038287-B       ,
Engineer Boranian,, Paul; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/24/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 4/29/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Partial Approval JESUS PINEDA
PLUMBING-Rough 5/20/2024 Corrections Issued JESUS PINEDA
PLUMBING-Rough 5/22/2024 Corrections Issued JESUS PINEDA
PLUMBING-Rough 5/28/2024 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 8/19/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 9/18/2024 Corrections Issued DANIEL VERA
ELECTRICAL-Rough 9/25/2024 Approved DANIEL VERA
PLUMBING-Rough 9/25/2024 Not Ready for Inspection DANIEL VERA
HVAC-Rough 10/2/2024 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 10/2/2024 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 10/22/2024 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Not Ready for Inspection DANIEL VERA
Green Building Rough 10/22/2024 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 10/30/2024 Not Ready for Inspection DANIEL VERA
Green Building Rough 10/30/2024 Not Ready for Inspection DANIEL VERA
HVAC-Rough 10/30/2024 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 10/30/2024 Not Ready for Inspection DANIEL VERA
HVAC-Rough 11/4/2024 Approved DANIEL VERA
PLUMBING-Rough 11/4/2024 Corrections Issued DANIEL VERA
ELECTRICAL-Rough 11/5/2024 Corrections Issued DANIEL VERA
Interior/Exterior Lathing 11/5/2024 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 11/8/2024 Approved DANIEL VERA
Interior/Exterior Lathing 11/8/2024 Partial Approval DANIEL VERA
PLUMBING-Rough 11/8/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 11/12/2024 Approved DANIEL VERA
Green Building Rough 11/12/2024 Approved DANIEL VERA
Insulation 11/18/2024 Approved REGINA MENDEZ
Shower Pan 11/21/2024 Approved DANIEL VERA
Interior/Exterior Lathing 11/26/2024 Approved REGINA MENDEZ
Drywall Nailing 11/27/2024 Corrections Issued REGINA MENDEZ
Drywall Nailing 8/21/2025 Not Ready for Inspection KIRK SANDERS
Final 8/21/2025 Corrections Issued KIRK SANDERS
Green Building Final 8/21/2025 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 8/21/2025 Not Ready for Inspection KIRK SANDERS
Drywall Nailing 8/26/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Final 8/26/2025 Corrections Issued STEPHANIE SWANSON
Final 8/26/2025 Partial Approval STEPHANIE SWANSON
Green Building Final 8/26/2025 Approved STEPHANIE SWANSON
HVAC-Final 8/26/2025 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 8/26/2025 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 8/26/2025 Approved STEPHANIE SWANSON
Final 9/19/2025 Corrections Issued KIRK SANDERS
Final 10/6/2025 OK to Issue CofO KIRK SANDERS