2755 S GRANVILLE AVE 90064
Certificate Information: 2755 S GRANVILLE AVE 90064
- Application / Permit
- 23014-10000-05064
- Plan Check / Job No.
- B23LA22600
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 2/16/2024
- Issuing Office
- Current Status
- CofO Issued on 10/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | DANIEL YIP |
| Corrections Issued | 12/9/2023 | DANIEL YIP |
| Quality Review Completed | 12/11/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 2/13/2024 | DANIEL YIP |
| Plan Check Approved | 2/14/2024 | DANIEL YIP |
| Issued | 2/16/2024 | APPLICANT |
| CofO in Progress | 10/6/2025 | KIRK SANDERS |
| Permit Finaled | 10/21/2025 | RICHARD STEINBACH |
| CofO Issued | 10/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/13/2023 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2023 | LIAM ODONOVAN |
| Specific Plan | Cleared | 1/29/2024 | MOHAMMAD HASAN |
Contact Information
| Contractor | Bela Remodeling; Lic. No.: 1038287-B | , |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/24/2024 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 4/29/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 5/20/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 5/22/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 5/28/2024 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 8/19/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 9/18/2024 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Rough | 9/25/2024 | Approved | DANIEL VERA |
| PLUMBING-Rough | 9/25/2024 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 10/2/2024 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 10/2/2024 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 10/22/2024 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 10/22/2024 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 10/30/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 10/30/2024 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 10/30/2024 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 10/30/2024 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 11/4/2024 | Approved | DANIEL VERA |
| PLUMBING-Rough | 11/4/2024 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Rough | 11/5/2024 | Corrections Issued | DANIEL VERA |
| Interior/Exterior Lathing | 11/5/2024 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 11/8/2024 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 11/8/2024 | Partial Approval | DANIEL VERA |
| PLUMBING-Rough | 11/8/2024 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 11/12/2024 | Approved | DANIEL VERA |
| Green Building Rough | 11/12/2024 | Approved | DANIEL VERA |
| Insulation | 11/18/2024 | Approved | REGINA MENDEZ |
| Shower Pan | 11/21/2024 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 11/26/2024 | Approved | REGINA MENDEZ |
| Drywall Nailing | 11/27/2024 | Corrections Issued | REGINA MENDEZ |
| Drywall Nailing | 8/21/2025 | Not Ready for Inspection | KIRK SANDERS |
| Final | 8/21/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 8/21/2025 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/21/2025 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 8/21/2025 | Not Ready for Inspection | KIRK SANDERS |
| Drywall Nailing | 8/26/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/26/2025 | Corrections Issued | STEPHANIE SWANSON |
| Final | 8/26/2025 | Partial Approval | STEPHANIE SWANSON |
| Green Building Final | 8/26/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 8/26/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 8/26/2025 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 8/26/2025 | Approved | STEPHANIE SWANSON |
| Final | 9/19/2025 | Corrections Issued | KIRK SANDERS |
| Final | 10/6/2025 | OK to Issue CofO | KIRK SANDERS |