836 S BURNSIDE AVE 90036

Certificate Information: 836 S BURNSIDE AVE 90036

Application / Permit
23014-10000-05031
Plan Check / Job No.
B23LA23165
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND INTERIOR REMODEL TO EXISTING 1 SFD TO ENCLOSE 15 SF UNDER EXISTING ROOF
Permit Issued
Issued on 12/18/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 ADAM HEGAZI
Corrections Issued 12/7/2023 ADAM HEGAZI
Plan Check Approved 12/14/2023 LUKE GONZALES
Issued 12/18/2023 APPLICANT
CofO in Progress 5/14/2026 RONNIE MINDANAO
CofO Issued 5/14/2026 DEROLD HAUFF
Permit Finaled 5/14/2026 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 12/11/2023 ERIK VAN BREENE
HPOZ Cleared 12/11/2023 ERIK VAN BREENE

Contact Information

Contractor Aggregate Construction Group; Lic. No.: 1034714-B 10930 ASHTON AVE 207      LOS ANGELES, CA 90024
Engineer Dorier,, David Julienmichel; Lic. No.: S7064 950 S GRAND AVE 4TH FLOOR      LOS ANGELES, CA 90015

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/29/2023 Approved RICHARD DOCKUS
Deputy Drilled-In Anchors 1/8/2024 Conditional Approval RICHARD DOCKUS
Footing/Foundation/Slab 1/8/2024 Corrections Issued RICHARD DOCKUS
METHANE-Barrier 1/8/2024 Approved RICHARD DOCKUS
METHANE-Subgrade 1/8/2024 Approved RICHARD DOCKUS
Footing/Foundation/Slab 1/10/2024 Approved RICHARD DOCKUS
HVAC-Rough 3/5/2025 Corrections Issued RONNIE MINDANAO
PLUMBING-Rough 3/5/2025 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Rough 3/10/2025 Approved RONNIE MINDANAO
HVAC-Rough 3/11/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/11/2025 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 3/12/2025 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Not Ready for Inspection RONNIE MINDANAO
Green Building Rough 3/12/2025 Not Ready for Inspection RONNIE MINDANAO
METHANE-Rough 3/12/2025 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 3/14/2025 Partial Approval JOSE MACIAS
Wood Frame 4/21/2025 Corrections Issued RONNIE MINDANAO
Deputy Drilled-In Anchors 5/12/2025 Conditional Approval RONNIE MINDANAO
Interior/Exterior Lathing 5/19/2025 Not Ready for Inspection RONNIE MINDANAO
Interior/Exterior Lathing 5/28/2025 Partial Approval JOSH MEISTER
Insulation 6/17/2025 Corrections Issued RONNIE MINDANAO
Drywall Nailing 6/27/2025 Approved RONNIE MINDANAO
Insulation 7/1/2025 Approved RONNIE MINDANAO
Interior/Exterior Lathing 7/29/2025 Approved ANTHONY RAMOS
Shower Pan 7/29/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 3/11/2026 Corrections Issued RONNIE MINDANAO
HVAC-Final 3/11/2026 Corrections Issued RONNIE MINDANAO
BUILDING-Rough-Frame 3/17/2026 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/17/2026 Not Ready for Inspection ENRIQUE MIRELES
Final 3/17/2026 Corrections Issued ENRIQUE MIRELES
Green Building Final 3/17/2026 Approved ENRIQUE MIRELES
Green Building Rough 3/17/2026 Approved ENRIQUE MIRELES
HVAC-Final 3/17/2026 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 3/17/2026 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 3/17/2026 Approved ENRIQUE MIRELES
Final 3/19/2026 Corrections Issued RONNIE MINDANAO
Final 4/29/2026 Partial Approval RONNIE MINDANAO
Final 5/7/2026 Partial Approval RONNIE MINDANAO
Final 5/11/2026 OK to Issue CofO RONNIE MINDANAO