2427 E SHOREDALE AVE 90031
Certificate Information: 2427 E SHOREDALE AVE 90031
- Application / Permit
- 23014-10000-05026
- Plan Check / Job No.
- B23LA23149
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION AND REMODEL TO (E) 1-STORY FRONT SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 6/25/2024
- Issuing Office
- Current Status
- CofO Issued on 8/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2023 | DANIEL YIP |
| Corrections Issued | 1/4/2024 | DANIEL YIP |
| Quality Review Completed | 1/4/2024 | KEN GILL |
| Building Plans Picked Up | 1/11/2024 | APPLICANT |
| Plan Check Approved | 4/2/2024 | DANIEL YIP |
| Issued | 6/25/2024 | APPLICANT |
| CofO in Progress | 7/30/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 8/1/2025 | DEROLD HAUFF |
| CofO Issued | 8/1/2025 | DEROLD HAUFF |
| Permit Finaled | 8/1/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/22/2024 | RICARDO BOHORQUEZ |
| Sewer availability | Cleared | 1/23/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2024 | JILVER MAZARIEGOS |
| ZI | Cleared | 2/5/2024 | NELSON RODRIGUEZ |
| Low Impact Development (LID) | Cleared | 3/21/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 3/22/2024 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/9/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/19/2024 | Corrections Issued | BRENDAN MORELLI |
| Deputy Drilled-In Anchors | 9/5/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Pre-Inspection | 9/6/2024 | Approved | LUIS CASTRO |
| Underground Mechanical | 9/25/2024 | Approved | LUIS CASTRO |
| Insulation | 9/26/2024 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | No Access for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 11/12/2024 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 11/12/2024 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 11/18/2024 | Approved | LUIS CASTRO |
| HVAC-Rough | 11/21/2024 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 11/21/2024 | Approved | LUIS CASTRO |
| Rough-Elec/Plmb/HVAC | 11/21/2024 | Corrections Issued | LUIS CASTRO |
| Underground Mechanical | 11/21/2024 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 11/25/2024 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 11/25/2024 | Not Ready for Inspection | ROY SPAULDING |
| Underground Mechanical | 11/25/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 11/27/2024 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 12/5/2024 | Corrections Issued | LUIS CASTRO |
| Green Building Rough | 12/5/2024 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 12/10/2024 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 12/11/2024 | Approved | LUIS CASTRO |
| Insulation | 12/11/2024 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 12/11/2024 | Approved | LUIS CASTRO |
| Drywall Nailing | 12/20/2024 | Corrections Issued | WILLIAM SIERRA |
| Drywall Nailing | 12/26/2024 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 1/7/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 1/24/2025 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 3/25/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 6/6/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/6/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 6/6/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/6/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 6/25/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 6/25/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/25/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Final | 7/24/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 7/24/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/24/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 7/30/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |