4552 N MURIETTA AVE 91423

Certificate Information: 4552 N MURIETTA AVE 91423

Application / Permit
23014-10000-05019
Plan Check / Job No.
B23LA23113
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 14'6" X 33' ADDITION TO (E) DETACHED ACCESSORY DWELLING UNIT TO ADD (2) NEW BEDROOMS AND (1) NEW BATHROOM PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER ARCHITECT DESIGN.
Permit Issued
Issued on 12/22/2023
Issuing Office
Current Status
CofO Issued on 5/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2023 APPLICANT
Assigned to Plan Check Engineer 12/11/2023 MADISON ODELL
Corrections Issued 12/12/2023 MADISON ODELL
Applicant returned to address corrections 12/16/2023 MADISON ODELL
Plan Check Approved 12/22/2023 MADISON O'DELL
Issued 12/22/2023 APPLICANT
CofO in Progress 5/1/2024 MISAEL ESPARZA
Permit Finaled 5/16/2024 RUBEN SALAS
Permit Finaled 5/16/2024 RUBEN SALAS
CofO Issued 5/16/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/12/2023 GABRIELLA TORRES
Eng Process Fee Ord 176,300 Cleared 12/13/2023 GABRIELLA TORRES
Sewer availability Cleared 12/13/2023 GABRIELLA TORRES
ZI Cleared 12/14/2023 ASHLEY RODARTE

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Oceanside Builders; Lic. No.: 983488-B       ,
Contractor Ys Builders Inc; Lic. No.: 983488-B       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/14/2024 Approved MISAEL ESPARZA
Footing/Foundation/Slab 2/14/2024 Approved MISAEL ESPARZA
Underground Mechanical 2/14/2024 Partial Approval MISAEL ESPARZA
Underground Mechanical 2/20/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/22/2024 Corrections Issued MISAEL ESPARZA
Underground Mechanical 2/22/2024 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 3/6/2024 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 3/6/2024 Approved MISAEL ESPARZA
HVAC-Rough 3/6/2024 Approved MISAEL ESPARZA
MERV13>=Rough 3/6/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 3/6/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/11/2024 Approved MISAEL ESPARZA
Insulation 3/14/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/14/2024 Approved MISAEL ESPARZA
Drywall Nailing 3/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 3/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 4/17/2024 Corrections Issued MISAEL ESPARZA
MERV13>=Final 4/17/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/17/2024 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 4/17/2024 Approved MISAEL ESPARZA
Final 4/26/2024 Corrections Issued MISAEL ESPARZA
Final 4/30/2024 OK to Issue CofO MISAEL ESPARZA