3786 S ASHWOOD AVE 90066

Certificate Information: 3786 S ASHWOOD AVE 90066

Application / Permit
23014-10000-05012
Plan Check / Job No.
B23LA23081
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION (261 SQFT 17' x 16'5") AT THE REAR OF THE (E) SFD AND INTERIOR REMODEL.
Permit Issued
Issued on 1/24/2024
Issuing Office
Metro
Current Status
CofO Issued on 2/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2023 APPLICANT
Assigned to Plan Check Engineer 12/11/2023 KHUONG TRUONG
Corrections Issued 12/11/2023 KHUONG TRUONG
Plan Check Approved 1/24/2024 NGHI SU
Issued 1/24/2024 APPLICANT
CofO in Progress 1/30/2025 JESUS PINEDA
CofO Issued 2/12/2025 RICHARD STEINBACH
Permit Finaled 2/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/11/2023 KHUONG TRUONG
Eng Process Fee Ord 176,300 Cleared 12/20/2023 DARIN LAM
Sewer availability Cleared 12/20/2023 DARIN LAM
Low Impact Development (LID) Cleared 1/22/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 1/23/2024 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/28/2024 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 3/1/2024 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 3/27/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 3/27/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 5/16/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 5/16/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/16/2024 Approved JESUS RODRIGUEZ
Deputy Wood Construction 6/6/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Approved JESUS RODRIGUEZ
Insulation 6/6/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/6/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 6/14/2024 Approved JESUS RODRIGUEZ
Green Building Rough 6/14/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/25/2024 Approved HERBERT GIRON
Footing/Foundation/Slab 7/19/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/24/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 7/24/2024 Approved JESUS RODRIGUEZ
Wood Frame 7/24/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/25/2024 Approved JESUS RODRIGUEZ
Final 9/27/2024 Corrections Issued JESUS PINEDA
Green Building Final 9/27/2024 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Approved JESUS PINEDA
Smoke Detectors 9/27/2024 Approved JESUS PINEDA
Final 1/27/2025 Not Ready for Inspection JESUS PINEDA
Green Building Final 1/27/2025 Approved JESUS PINEDA
Final 1/30/2025 OK to Issue CofO JESUS PINEDA