7551 S STEWART AVE 90045

Certificate Information: 7551 S STEWART AVE 90045

Application / Permit
23014-10000-04983
Plan Check / Job No.
B23LA22989
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: REMODEL TO AN (E) TWO STORY SINGLE FAMILLY DWELLING.
Permit Issued
Issued on 5/9/2024
Issuing Office
Current Status
Permit Finaled on 1/2/2025

Permit Application Status History

Submitted 12/7/2023 APPLICANT
Assigned to Plan Check Engineer 12/13/2023 GEORGE JOLAKIAN
Corrections Issued 12/14/2023 RACHEL BEYENE
Quality Review Completed 12/14/2023 GARO TELMI
Applicant returned to address corrections 3/20/2024 GEORGE JOLAKIAN
Plan Check Approved 5/9/2024 GEORGE JOLAKIAN
Issued 5/9/2024 APPLICANT
Permit Finaled 12/31/2024 TEMISTOCLES CAAL

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/22/2024 CHARLES POWELL

Contact Information

Contractor Bela Remodeling; Lic. No.: 1038287-B       ,
Engineer Boranian,, Paul; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/3/2024 Partial Inspection BOBBY KEY
Deputy Drilled-In Anchors 9/9/2024 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 9/10/2024 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 9/13/2024 Approved BOBBY KEY
ELECTRICAL-Rough 10/10/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 10/10/2024 Partial Approval TEMISTOCLES CAAL
Wood Frame 10/10/2024 Not Ready for Inspection TEMISTOCLES CAAL
Gas Test 10/15/2024 Approved BOBBY KEY
HVAC-Rough 10/15/2024 Not Ready for Inspection BOBBY KEY
Insulation 10/15/2024 Approved BOBBY KEY
Wood Frame 10/15/2024 Partial Approval BOBBY KEY
Deputy Wood Construction 10/17/2024 Conditional Approval BOBBY KEY
Wood Frame 11/6/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 11/13/2024 Approved TEMISTOCLES CAAL
Gas Test 12/16/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 12/31/2024 Approved TEMISTOCLES CAAL
Final 12/31/2024 Permit Finaled TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 12/31/2024 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 12/31/2024 Approved TEMISTOCLES CAAL