13542 N VALLEYHEART DR 91423

Certificate Information: 13542 N VALLEYHEART DR 91423

Application / Permit
23014-10000-04974
Plan Check / Job No.
B23LA22952
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 50'-0"x 24'-9" IRREG.SHAPED ADDITION TO (E) SFD AND INTERIOR REMODEL. WORK DONE PER ENGINEER DESIGN. **NFPA-13D FIRE SPRINKLERS TO BE INSTALLED THROUGHOUT**
Permit Issued
Issued on 1/18/2024
Issuing Office
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2023 APPLICANT
Assigned to Plan Check Engineer 12/8/2023 MIROOSH KHACHATOORIAN
Corrections Issued 12/9/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 1/18/2024 MIROOSH KHACHATOORIAN
Issued 1/18/2024 APPLICANT
CofO in Progress 11/4/2024 MISAEL ESPARZA
Permit Finaled 11/13/2024 DANIEL ORRANTE
CofO Issued 11/13/2024 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development (LID) Cleared 1/4/2024 SAMUEL LINN
ZI Cleared 1/4/2024 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 1/16/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 1/16/2024 CARLOS RAMIREZ
Sewer availability Cleared 1/16/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/23/2024 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 3/6/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 3/11/2024 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/13/2024 Approved MISAEL ESPARZA
Deputy Other (see comments) 5/7/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 5/9/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Corrections Issued MISAEL ESPARZA
MERV13>=Rough 5/9/2024 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 5/10/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Partial Approval MISAEL ESPARZA
Wood Frame 5/14/2024 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 6/6/2024 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 6/6/2024 Approved JOHN COLEMAN
MERV13>=Rough 6/6/2024 Approved JOHN COLEMAN
PLUMBING-Rough 6/6/2024 Approved JOHN COLEMAN
Insulation 6/12/2024 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 6/12/2024 Partial Approval MISAEL ESPARZA
Shower Pan 6/12/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/17/2024 Approved MISAEL ESPARZA
HVAC-Rough 6/17/2024 Approved MISAEL ESPARZA
Drywall Nailing 6/24/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 6/24/2024 Approved SALVADOR MARTINEZ
Deck 8/22/2024 Partial Inspection MISAEL ESPARZA
Pre-Inspection 9/11/2024 Partial Inspection MISAEL ESPARZA
Final 9/25/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/25/2024 Approved MISAEL ESPARZA
MERV13>=Final 9/25/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/25/2024 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 9/25/2024 Approved MISAEL ESPARZA
Final 10/15/2024 Corrections Issued MISAEL ESPARZA
Final 10/17/2024 Not Ready for Inspection MISAEL ESPARZA
Final 10/31/2024 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 10/31/2024 Approved MISAEL ESPARZA