3255 S CASTLE HEIGHTS AVE 90034
Certificate Information: 3255 S CASTLE HEIGHTS AVE 90034
- Application / Permit
- 23014-10000-04969
- Plan Check / Job No.
- B23LA22943
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERSION OF EXISTING GARAGE TO AN ADU, WITH ATTACHED TRELLIS (158 SQ FT). DETACHED ADU PER LAMC 12.22 A.33 (c) and (d).
- Permit Issued
- Issued on 8/27/2024
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | ADRIANA LOPEZ |
| Corrections Issued | 1/10/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 1/26/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 7/18/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 8/13/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 8/16/2024 | ADRIANA LOPEZ |
| Issued | 8/27/2024 | APPLICANT |
| Permit Finaled | 7/8/2025 | RICHARD STEINBACH |
| CofO Issued | 7/8/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/8/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/14/2024 | VASIL MIHALEV |
| Address approval | Cleared | 2/20/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2024 | DARIN LAM |
| Sewer availability | Cleared | 2/20/2024 | DARIN LAM |
| Specific Plan | Cleared | 3/6/2024 | FREDDY GARCIA |
| Construction near power lines | Cleared | 4/8/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 6/11/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 8/13/2024 | DARIN LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Terrio,, Greyson Franklin; Lic. No.: NA87383 | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/24/2024 | Partial Approval | ASHLEY THOMPSON |
| Pre-Inspection | 9/24/2024 | Partial Approval | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 10/4/2024 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 10/4/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 10/8/2024 | Conditional Approval | ASHLEY THOMPSON |
| Special/Order Compliance | 10/8/2024 | Partial Approval | REGINA MENDEZ |
| Underground Mechanical | 10/11/2024 | Partial Approval | REGINA MENDEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 11/5/2024 | Not Ready for Inspection | KIRK SANDERS |
| MERV13>=Rough | 11/5/2024 | Not Ready for Inspection | KIRK SANDERS |
| Deputy Wood Construction | 11/8/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/26/2024 | Partial Approval | ARAM AVEDISIAN |
| MERV13>=Rough | 11/26/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/3/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 12/3/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 12/3/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 12/3/2024 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/3/2024 | Corrections Issued | ASHLEY THOMPSON |
| Wood Frame | 12/3/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/6/2024 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/6/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/6/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 12/6/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/6/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/6/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/11/2024 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 12/11/2024 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/18/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 12/18/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 12/18/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 12/23/2024 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 3/14/2025 | Partial Inspection | BOBBY KEY |
| ELECTRICAL-Final | 6/9/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 6/9/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 6/9/2025 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Final | 6/24/2025 | Corrections Issued | ASHLEY THOMPSON |
| Final | 6/24/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 6/24/2025 | Approved | ASHLEY THOMPSON |
| Gas Test | 6/24/2025 | Approved | ASHLEY THOMPSON |
| Green Building Final | 6/24/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 6/24/2025 | Approved | ASHLEY THOMPSON |
| MERV13>=Final | 6/24/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 6/24/2025 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 6/24/2025 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 6/24/2025 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 7/1/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 7/1/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 7/1/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 7/1/2025 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 7/7/2025 | Approved | ASHLEY THOMPSON |
| Final | 7/7/2025 | Conditional Approval | ASHLEY THOMPSON |
| HVAC-Final | 7/7/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 7/7/2025 | Approved | ASHLEY THOMPSON |