778 W 2ND ST 90731

Certificate Information: 778 W 2ND ST 90731

Application / Permit
23014-10000-04964
Plan Check / Job No.
B23LA22910
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED TWO BEDROOMS AND TWO BATHROOMS ADDITION AT FRONT OF REAR UNIT.
Permit Issued
Issued on 3/8/2024
Issuing Office
Metro
Current Status
CofO Issued on 2/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2023 APPLICANT
Assigned to Plan Check Engineer 12/11/2023 LAWRENCE QUIRANTE
Corrections Issued 12/13/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 12/15/2023 APPLICANT
Applicant returned to address corrections 2/7/2024 KHUONG TRUONG
Plan Check Approved 3/1/2024 SAMUEL GONZALEZ
Issued 3/8/2024 APPLICANT
CofO in Progress 2/4/2025 JOSEPH MCGARRY
CofO Issued 2/4/2025 ANSON MAGLASANG
Permit Finaled 2/4/2025 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/26/2024 JILVER MAZARIEGOS
Grading Pre-Inspection Cleared 1/31/2024 SERGIO VALENZUELA
Eng Process Fee Ord 176,300 Cleared 2/5/2024 KHAING AYE

Contact Information

Contractor De La Rosa Construction; Lic. No.: 855010-B 3627 E FIRST STREET      LOS ANGELES, CA 90063
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/1/2024 Not Ready for Inspection JAMES CHAVEZ
Footing/Foundation/Slab 4/1/2024 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 4/15/2024 Approved JAMES CHAVEZ
PLUMBING-Rough 4/25/2024 Partial Approval EUGENE CASSIDY
Sewer 4/25/2024 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Partial Approval JAMES CHAVEZ
Insulation 4/29/2024 Partial Approval JAMES CHAVEZ
BUILDING-Rough-Frame 6/24/2024 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Rough 6/24/2024 Corrections Issued ANSON MAGLASANG
Green Building Rough 6/24/2024 Not Ready for Inspection ANSON MAGLASANG
HVAC-Rough 6/24/2024 Approved ANSON MAGLASANG
PLUMBING-Rough 6/24/2024 Approved ANSON MAGLASANG
Rough-Elec/Plmb/HVAC 6/24/2024 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 7/12/2024 Approved JAMES CHAVEZ
ELECTRICAL-Rough 7/12/2024 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Partial Approval JAMES CHAVEZ
Green Building Rough 7/12/2024 Approved JAMES CHAVEZ
Grounding or Bonding 7/12/2024 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 7/12/2024 Approved JAMES CHAVEZ
PLUMBING-Rough 7/12/2024 Approved JAMES CHAVEZ
Rough-Elec/Plmb/HVAC 7/12/2024 Not Ready for Inspection JAMES CHAVEZ
Sewer 7/12/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 7/23/2024 Partial Approval JAMES CHAVEZ
Insulation 8/8/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/8/2024 Approved JOSEPH MCGARRY
Drywall Nailing 9/23/2024 Approved JOSEPH MCGARRY
Service/Power Release 9/23/2024 Not Required JOSEPH MCGARRY
Underground Mechanical 9/23/2024 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Final 10/29/2024 Approved JOSEPH MCGARRY
Final 1/16/2025 Corrections Issued BEN MOLSTAD
Green Building Final 1/16/2025 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 1/16/2025 SGSOV Approved BEN MOLSTAD
Smoke Detectors 1/16/2025 Approved BEN MOLSTAD
Final 1/24/2025 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 1/24/2025 Approved JOSEPH MCGARRY