2220 N OROS ST 90031

Certificate Information: 2220 N OROS ST 90031

Application / Permit
23014-10000-04963
Plan Check / Job No.
B23LA22894
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION AND CONVERT (E) GARAGE TO 2-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 4/15/2024
Issuing Office
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 DANIEL YIP
Corrections Issued 12/10/2023 DANIEL YIP
Quality Review Completed 12/11/2023 PRANITA SHAH
Applicant returned to address corrections 1/12/2024 DANIEL YIP
Plan Check Approved 2/21/2024 DANIEL YIP
Issued 4/15/2024 APPLICANT
CofO in Progress 6/11/2025 FREDDIE RIVERA
No Progress 6/11/2025 DEROLD HAUFF
No Progress 6/12/2025 DEROLD HAUFF
No Progress 7/13/2025 DEROLD HAUFF
CofO in Progress 7/13/2025 DEROLD HAUFF
Permit Finaled 7/16/2025 DEROLD HAUFF
CofO Issued 7/16/2025 DEROLD HAUFF
Permit Finaled 7/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/21/2023 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 12/21/2023 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 12/27/2023 CHRISTINA BRACO
Sewer availability Cleared 12/27/2023 CHRISTINA BRACO
ZI Cleared 1/2/2024 MAYELA VILLA
Construction near power lines Cleared 4/10/2024 RIDWAN HARDY

Contact Information

Contractor C W Remodeling Inc; Lic. No.: 1034250-B 11008 RIVERSIDE DR SUITE A      TOLUCA LAKE, CA 91602
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/30/2024 Partial Inspection THOMAS LOGRASSO
Special/Order Compliance 5/1/2024 Corrections Issued THOMAS LOGRASSO
Pre-Inspection 7/19/2024 Partial Inspection HAMIK HARTOUNIAN
Underground Mechanical 7/19/2024 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/25/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/28/2024 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 8/28/2024 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 9/27/2024 Corrections Issued LUIS CASTRO
BUILDING-Rough-Frame 2/20/2025 Not Ready for Inspection CRAIG DAVIS
Drywall Nailing 2/20/2025 Partial Inspection CRAIG DAVIS
ELECTRICAL-Final 2/20/2025 Not Ready for Inspection CRAIG DAVIS
Final 2/20/2025 Not Ready for Inspection CRAIG DAVIS
Green Building Final 2/20/2025 Corrections Issued CRAIG DAVIS
Green Building Rough 2/20/2025 Approved CRAIG DAVIS
MERV13>=Final 2/20/2025 Not Ready for Inspection CRAIG DAVIS
MERV13>=Rough 2/20/2025 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Final 2/20/2025 Approved CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 2/20/2025 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 2/20/2025 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 5/8/2025 Approved FREDDIE RIVERA
Drywall Nailing 5/8/2025 Approved FREDDIE RIVERA
ELECTRICAL-Final 5/8/2025 Approved FREDDIE RIVERA
Final 5/8/2025 Corrections Issued FREDDIE RIVERA
Green Building Final 5/8/2025 Approved FREDDIE RIVERA
HVAC-Final 5/8/2025 Approved FREDDIE RIVERA
MERV13>=Final 5/8/2025 Approved FREDDIE RIVERA
MERV13>=Rough 5/8/2025 Approved FREDDIE RIVERA
PLUMBING-Final 5/8/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Approved FREDDIE RIVERA
Service/Power Release 5/8/2025 Approved FREDDIE RIVERA
Smoke Detectors 5/8/2025 Approved FREDDIE RIVERA
Final 6/5/2025 OK to Issue CofO FREDDIE RIVERA