2220 N OROS ST 90031
Certificate Information: 2220 N OROS ST 90031
- Application / Permit
- 23014-10000-04963
- Plan Check / Job No.
- B23LA22894
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND CONVERT (E) GARAGE TO 2-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 4/15/2024
- Issuing Office
- Current Status
- CofO Issued on 7/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | DANIEL YIP |
| Corrections Issued | 12/10/2023 | DANIEL YIP |
| Quality Review Completed | 12/11/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 1/12/2024 | DANIEL YIP |
| Plan Check Approved | 2/21/2024 | DANIEL YIP |
| Issued | 4/15/2024 | APPLICANT |
| CofO in Progress | 6/11/2025 | FREDDIE RIVERA |
| No Progress | 6/11/2025 | DEROLD HAUFF |
| No Progress | 6/12/2025 | DEROLD HAUFF |
| No Progress | 7/13/2025 | DEROLD HAUFF |
| CofO in Progress | 7/13/2025 | DEROLD HAUFF |
| Permit Finaled | 7/16/2025 | DEROLD HAUFF |
| CofO Issued | 7/16/2025 | DEROLD HAUFF |
| Permit Finaled | 7/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/21/2023 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 12/21/2023 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 12/27/2023 | CHRISTINA BRACO |
| ZI | Cleared | 1/2/2024 | MAYELA VILLA |
| Construction near power lines | Cleared | 4/10/2024 | RIDWAN HARDY |
Contact Information
| Contractor | C W Remodeling Inc; Lic. No.: 1034250-B | 11008 RIVERSIDE DR SUITE A TOLUCA LAKE, CA 91602 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/30/2024 | Partial Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 5/1/2024 | Corrections Issued | THOMAS LOGRASSO |
| Pre-Inspection | 7/19/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 7/19/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/25/2024 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/28/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/28/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/27/2024 | Corrections Issued | LUIS CASTRO |
| BUILDING-Rough-Frame | 2/20/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Drywall Nailing | 2/20/2025 | Partial Inspection | CRAIG DAVIS |
| ELECTRICAL-Final | 2/20/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 2/20/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 2/20/2025 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 2/20/2025 | Approved | CRAIG DAVIS |
| MERV13>=Final | 2/20/2025 | Not Ready for Inspection | CRAIG DAVIS |
| MERV13>=Rough | 2/20/2025 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Final | 2/20/2025 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/20/2025 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 2/20/2025 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 5/8/2025 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 5/8/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 5/8/2025 | Approved | FREDDIE RIVERA |
| Final | 5/8/2025 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 5/8/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 5/8/2025 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 5/8/2025 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 5/8/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 5/8/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 5/8/2025 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 5/8/2025 | Approved | FREDDIE RIVERA |
| Final | 6/5/2025 | OK to Issue CofO | FREDDIE RIVERA |